On Schedule

Many of these actions have annual outputs, with elements due to date successfully delivered.

No.ActionProposed OutputSMP DeadlineStatusProgressASI
01Develop and publish an annual public transport passenger safety and personal security report and implement measures where appropriate.2022 Report developed. 2023 First report published. 2024 and 2025 Annual reports published2025 Q4On ScheduleReport content was developed in 2022 and first report was published in Q1 2024; see https://www.nationaltransport. ie/publications/nta-security- report-2023/. The NTA is currently working with public transport operators to develop an implementation plan addressing some of the key recommendations in the March 2024 report. This plan is expected to be finalised in Q3 or early Q4 this year, after which the NTA hope to proceed with the implementation of the agreed measures, subject to funding. The second Annual Public Transport Security Report is on track and scheduled for publication in the first half of 2025.Shift
02Continue awareness campaigns with the aim of promoting inclusivity, courtesy and respect for all when travelling on public transport.Annual Campaigns2025 Q4On Schedule2022 included an anti-racism campaign, a campaign to support people with hidden disabilities and Support for Pride in June. 2023 included campaigns supporting users with disabilities, staff respect and anti-racism. A wheelchair priority campaign also ran. 2024 will include passenger etiquette, anti-racism, staff respect and autism inclusion campaigns.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
03Continue to protect and renew rail infrastructure through the Infrastructure Manager Multi-Annual Contract (IMMAC).2024 Existing IMMAC reviewed. 2025 IMMAC 2025- 2029 agreed2025 Q4On SchedulePreliminary discussions underway with Iarnród Éireann regarding mid-term review of current contract. Iarnród Éireann to consider requirements for maintaining ‘steady state’ under 2025- 2029 contract.Shift
05Expand speed management measures on National, Regional and Local roads using Periodic Speed Limits at schools, Vehicle Activated Signs and Average Speed Cameras in collaboration with An Garda Síochána at appropriate high-risk locations. (RSS action 8)2024 Q4On ScheduleTII are leading the development of the first National Safety Camera Strategy and associated site selection handbook, supported by a cross-agency working group. This strategy, which is due for completion by the end of 2024, will provide the framework for the long-term deployment of safety cameras, both for speed and other offences. In the short-term An Garda Síochána has budget approval to maintain the 20% increase in GoSafe camera hours announced in September 2023 until October 2025, as well as for three additional average speed camera locations and nine static camera locations.Shift
08Deliver fuelling/charging infrastructure to support operation of zero emission public bus fleet.Fuelling and charging infrastructure in place for public bus fleet.2025 Q4On ScheduleIn progress, with depot electirifcation complete in Athlone and works ongoing in Dublin and Limerick. Summerhill and Phibsborough depots electrified in Dublin. 34 electric buses in service in Limerick. More to come on stream incrementally.Improve
No.ActionProposed OutputSMP DeadlineStatusProgressASI
13Transition Dublin Metropolitan PSO bus services to low/zero emission bus fleet. (Complements CAP action 268)50% of fleet transitioned to low/zero emission vehicles.2025 Q4On ScheduleThere are currently 226 low- emission buses and 87 zero- emission buses in service; there are a further 167 zero- emission buses either on order or awaiting entry into service. These 480 buses are equivalent to approximately half of the Dublin Bus fleet as of Q4 2021.Improve
14Transition Cork, Galway, Limerick and Waterford metropolitan area PSO bus services to low/ zero emission bus fleet. (Complements CAP action 269)40% of fleet transitioned to low/zero emission vehicles.2025 Q4On ScheduleThere are currently 61 low- emission buses and 34 zero- emission buses in service; there are a further 87 zero- emission buses either on order or awaiting entry into service. These 182 buses are equivalent to more than 70% of the regional city PSO bus fleet operated by Bus Éireann in Cork, Galway, Limerick and Waterford as of Q4 2021.Improve
15Transition town and Local Link bus services to low/zero emission bus fleet. (Complements CAP actions 270 and 271)2022 First town transitioned to fully electric public bus service. 2025 Three additional towns transitioned to electrified bus services and 10% of Local Link services electrified.2025 Q4On ScheduleAthlone electric bus service was launched in January 2023. EU Just Transition Funding has been secured to assist with the decarbonisation of rural public transport services in the Midlands area. Electrification of Sligo Town bus service underway and discussions with Bus Éireann regarding electrification of further town bus services in Dundalk, Navan and Drogheda ongoing.Improve
No.ActionProposed OutputSMP DeadlineStatusProgressASI
19Deliver additional cycling infrastructure projects in the five cities. (Complements CAP action 233, RSS action 5)400 km GDA Network completed or under construction. 200 km Regional Cities Network completed or under construction.2025 Q4On ScheduleIn progress with c. 1,200 cycle schemes at design or implementation stage across the State. 305km have been delivered GDA network and 239km regional cities network. This output relates to Active Travel Infrastructure as a whole (pedestrian and cycle facilities).Shift
20Expand rail fleet capacity.2023 41 additional carriages placed into passenger service. 2025 95 DART+ carriages delivered.2025 Q4On ScheduleAll 41 ICRs delivered, all to commence passenger service in 2024. Design and development of new DART carriages continues and on schedule for delivery in 2025.Shift
26Develop pedestrian enhancement plans for the regional growth centres and key towns.Plans developed.2024 Q4On ScheduleInitial scoping work commenced - linked to Action 17Shift
27Develop and implement an active travel infrastructure programme for regional growth centres and key towns outside of the Greater Dublin Area. (Complements CAP action 233, RSS action 5, 40)2023 Urban cycle networks developed for all regional growth centres and key towns outside the GDA. 2025 100 km constructed or under construction in regional growth centres and key towns outside the GDA.2025 Q4On ScheduleCycle network plans have been developed for all counties, covering all regional growth centres and key towns. Following some amendments arising from the consultation process, the Strategic Environmental Assessment has been completed in Q1 2024, with statutory consultation undertaken during Q2 2024. Overall, there is 757km of cycle and 665 km of walking infrastructure in development with approximately 40% located outside the GDAShift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
30Expand greenway network establishing linkages with towns and villages in line with the strategic national cycle network. (Complements CAP action 231)350 km of greenway constructed or under construction.2025 Q4On ScheduleA total of 79km of new greenway has opened since publication of the SMP with a further 114km currently at construction.Shift
33Identify the potential for integration of non- emergency health transport services with the Local Link services by conducting and monitoring a pilot project in Leitrim to deliver nonemergency health transport services.Pilot completed and implementation strategy developed.2024 Q4On ScheduleThis is a 3-year pilot, with a formal commitment to review in 2024. NTA has commissioned independent review of the Pilot.Shift
34Develop and implement a programme of improved town bus services.Improved town bus services implemented in Carlow, Ennis, Letterkenny, Mullingar, Portlaoise.2025 Q4On ScheduleClonmel Town service was implemented in December 2023. Carlow Town CW1 and CW2 introduced on 30 July 2023. Procurement of a contractor to provide town services in Portlaoise has started. Planning continues in Ennis, Mullingar and Letterkenny.Shift
35Develop and commence delivery of an enhanced bus stop and bus shelter programme for regional and rural services. (Complements RSS action 71, 72)2022 Programme developed. 2025 200 additional bus shelters installed for regional and rural services.2025 Q4On ScheduleDuring 2022, a total of 126 shelters were installed against a target of 100. In 2023, 134 shelters were installed. 59 shelters delivered in Q1 of 2024.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
38Deliver public transport corridors providing prioritised bus lanes on national radial routes to the M50. (CAP action 261)Rollout of corridors commenced.2025 Q4On ScheduleN4 part 8 planning approval was confirmed in February 2023. Work is also progressing on design of the N11 bus priority scheme. The N11 bus priority measures are subject to environmental impact assessment and could therefore take up to 2 years to achieve planning approval.Avoid
41Develop and commence implementation of a programme for secure bicycle parking in key towns and cities plus transport hubs.2023 Programme developed. 2025 1,000 secure bicycle parking spaces implemented.2025 Q4On scheduleA substantial amount of implementation work is already ongoing, with secure cycle parking provision being made in car parks at train stations and at various bus stop locations. 11,109 cycle stands have been delivered to date in the GDA with a further 1,263 in Regional Cities. It should be noted that this figure includes all cycle parking stands funded through the Safe Routes to School programme.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
48Promote the principle of ‘Access for All’ across sustainable mobility services through:2022 Customer service officers provided on all inter-city trains 2025 Eight additional railway stations equipped with footbridge and lifts to allow all platform access. All bus stations equipped with wheelchair accessible bus bay. Wheelchair accessible stops for lift equipped coaches provided in additional 50 towns. 100 additional low floor vehicles for regional/ inter-city coach services introduced. Roll-out of new National Journey Planner commenced. Changing Places toilets installed at three additional transport hubs.2025 Q4On Schedule120 customer service officers have now been recruited by Irish Rail. Three stations completed in 2021, two stations in 2022. One station in 2023 and Banteer almost complete now. 26 stations with Wheelchair accessible stops on target to be completed. Wheelchair accessible stops for lift equipped coaches in progress. 103 double deck low floor coaches were ordered and put into service by the end of 2023. 30 more are in manufacture at present. New Journey Planner has been rolled out. Changing Places have been installed in 2 Rail Stations with 3 planned for 2024.Shift
49Expand the Travel Assistance Scheme beyond the GDA.2023 Scheme expanded to Cork. 2025 Scheme expanded to Galway, Limerick and Waterford.2025 Q4On ScheduleThe Pilot of the Travel Assistance Scheme Cork started taking bookings in September 2022. Scheme planned to be rolled out in Galway and Limerick later in 2024.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
50Expand the number of Wheelchair Accessible Vehicles in the SPSV fleet.WAVs expanded by 25%.2025 Q4On ScheduleAs of March 27th, there were 3,750 WAVs in the fleet. This represents a 15% increase in WAVs to date. NTA is currently on track to meet the target.Shift
76Ensure that the statutory reviews of the Regional Spatial and Economic Strategies include an analysis of land use development potential based on accessibility to each region’s proposed core public transport network.Review of RSES for the Eastern and Midland Region commenced.2025 Q4On ScheduleThe review of the RSES for the Eastern and Midland Region will commence in 2025.Avoid
77Prepare and commence implementation of local transport plans for regional growth centres and key towns having regard to the Area Based Transport Assessment Guidance Note.Local transport plans for regional growth centres and key towns completed.2025 Q4On ScheduleThe preparation by local authorities of Local Transport Plans for key towns and regional growth centres continues to progress and is on schedule for completion by Q4 2025.Avoid
86Develop National Consolidated Customer Contact Centre for Transport.Centre developed2025 Q4On ScheduleA contract mobilisation phase has commenced. There will be a phased transition, starting with Bus Éireann in Autumn 2024, with other operators joining later in the year.Shift

Delayed

No.ActionProposed OutputSMP DeadlineStatusProgressASI
06Conduct a review of road traffic policy and legislation to prioritise the safety of walking and cycling. (RSS action 43)2023 Q4DelayedThe Department has conducted some initial scoping of what Action 43 entails. Implementation of the Action will involve a comprehensive review of all road traffic legislation, and can happen only in the context of consolidation of the Acts. This Action is expected to be rolled in to the Road Safety Strategy Phase 2 Action Plan.Shift
09Develop a strategy for the transition of commercial and PSO long distance bus services to low emission technologies.Strategy framework developed2023 Q4DelayedAwaiting report from Market consultation for Zero-Emission Ramp-Accessible Coaches to inform adoption of overall strategy. Draft Strategy expected by 2025.Improve
No.ActionProposed OutputSMP DeadlineStatusProgressASI
12Commence delivery of DART+ Programme. (Complements Climate Action Plan (CAP) action 246)2022 DART+ West: Railway Order application submitted. DART+ South West: Railway Order application submitted. DART+ Coastal South: First round of public consultation completed. DART+ Coastal North: First and second rounds of public consultation completed. 2023 DART+ Coastal North: Railway Order application submitted. DART+ Coastal South: Second round of public consultation. DART+ Coastal South: Railway Order application submitted.2023 Q4DelayedRailway Order applications for DART+ West (July 2022) and DART+ South West (March 2023) have been submitted. DART+ Coastal North: First and second rounds of public consultation have been completed. Its Railway Order application was submitted in July 2024. Due to an evolving scope for the DART+ Coastal South project, this element of the DART+ programme is being progressed on a phased approach. The delivery timelines associated with the phasing are under review. DART+ West: Permission granted by An Bord Pleanála for the DART+ West line (July 2024).Shift
16Complete Strategic Rail Review to, inter alia, identify a pathway to appropriate decarbonisation of interurban rail services. (Complements CAP action 285)Review completed2022 Q4DelayedPublic consultation is complete. Next steps have been proposed, and Minister and Cabinet have approved. Published on 31 July 2024 - https://www.gov.ie/en/ publication/cc8fc-all-island- strategic-rail-review/.Improve
No.ActionProposed OutputSMP DeadlineStatusProgressASI
17Develop pedestrian enhancement plans for the five metropolitan areas.Plans developed2023 Q4DelayedThis project commenced at the end of March 2023. Draft final reports have been completed for all cities and are currently under review by the NTA.Shift
21Continue appraisal and planning for new light rail in Dublin and Cork, and consider the feasibility of light rail in Galway.2022 Emerging Preferred Route for Luas Cork identified. 2023 Planning application documentation completed for Luas Finglas. Assessment of light rail for Galway completed as part of review of Galway Transport Strategy.2023 Q4DelayedEmerging Preferred route for Luas Cork is close to finalising for consultation later in 2024. Preliminary Business Case and Draft Railway Order documentation for Luas Finglas in preparation and on target for submission in Q3 2024. Draft Galway Transport Strategy intended to be published for consultation by Q2 2025.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
23Commence delivery of BusConnects Core Bus Corridor Infrastructure Works in the five cities. (Complements CAP actions 241, 242, 243, 244)2022 Construction of Salmon Weir cycling and pedestrian bridge commenced as part of BusConnects Galway. Planning process for Cross City Link commenced as part of BusConnects Galway. 2023 Planning process for Dublin Road scheme commenced as part of BusConnects Galway. On-street construction of Radial Core Bus Corridor Schemes commenced as part of BusConnects Dublin.2023 Q4DelayedSalmon Weir Bridge opened in May 2023. The planning consent application to An Bord Pleanála in respect of Galway’s Cross City Link project was submitted in September 2022. Oral Hearing on Cross City Link held in February 2024. Planning application for Dublin Road expected by 2025.Shift
28Develop and publish cycle network plans for all counties. (Complements CAP action 231, RSS action 176)Plans published.2023 Q4DelayedCycle network plans have been developed for all counties, covering all regional growth centres and key towns. Following some amendments arising from the consultation process, finalisation of the Strategic Environmental Assessment is now underway. Statutory consultation in respect of Strategic Environmental Assessment due to take place in Q3 2024.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
40Develop demand management scheme for the Greater Dublin Area.GDA demand management scheme developed and published.2023 Q4DelayedThe development of this scheme is ongoing. Due to changes in the proposed consultation programme and alignment with National Demand Management Strategy, this will likely stretch into Q4 2024.Avoid
52Develop and implement an equitable fares strategy for all applicable subsidised services.2022 Strategy developed 2023 Implementation commenced2023 Q4DelayedFares strategy was published in April 2023. Phase 1 was successfully implemented on June 2024. Phase 2 expected to be implemented in Q1 of 2025.Shift
57Review, develop and update guidelines, standards and supporting legislation to allow for a range of solutions to be developed for road space reallocation/ redesign to repurpose existing legacy car- based road design.Delivery of updates completed2023 Q4DelayedWork in this area is ongoing and open-ended, encompassing a range of documents to be updated including DMURS advice notes and advice in relation to rapid buildouts.Avoid
60Expand continuous professional training for key design skills and application of national standards.2022 Online workshops carried out. 2023 Graduate training programme introduced2023 Q4Delayed8 online DMURS workshops took place in 2022 with over 3500 attendees. Development of the relevant graduate course is underway, and expected in late 2024.Shift
65Review and make recommendations on facilitating cyclists and pedestrians at junctions, including measures that do not require powered traffic signals. (RSS action 56)2022 Q4DelayedProgressing this Action was dependent on the completion of the National Cycle Network and the outcome of the Speed Limits Review. These are now complete and steps to implement this Action are under consideration.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
66Conduct a pilot (with supporting infrastructure) to examine the feasibility of introducing a ‘cyclist turning left on red’ provision. Take into account best international practice around other cycling priority measures and make recommendations. (RSS action 57)2022 Q4DelayedNew secondary legislation is required to undertake this pilot project.Shift
72Amend Section 17 of the Dublin Transport Authority Act 2008 to establish a National Transport Authority Advisory Council.Legislation amended2023 Q4DelayedWork is continuing on the legislative amendments required. Subject to Government and Oireachtas approvals, a revised approach to progress the required legislative changes via an amendment to a planned Bill before the Houses of the Oireachtas is being considered, in order to facilitate an accelerated passage through the legislative programme rather than progressing a new Bill / General Scheme.Shift
75Extend the statutory transport planning remit of the National Transport Authority to the metropolitan areas of Cork, Galway, Limerick and Waterford.Legislation to extend remit introduced.2023 Q4DelayedWork is continuing on the legislative amendments required. Subject to Government and Oireachtas approvals, a revised approach to progress the required legislative changes via an amendment to a planned Bill before the Houses of the Oireachtas is being considered, in order to facilitate an accelerated passage through the legislative programme rather than progressing a new Bill / General Scheme.Avoid
No.ActionProposed OutputSMP DeadlineStatusProgressASI
78Deliver metropolitan area transport strategies in the cities. (Complements CAP actions 254 and 256)2022 Limerick Shannon Metropolitan Area Transport Strategy published. Review of Transport Strategy for the Greater Dublin Area completed, Waterford Metropolitan Area Transport Strategy published. 2023 Review of Galway Transport Strategy completed. 2025 Review of Cork Metropolitan Area Transport Strategy commenced.2025 Q4DelayedLimerick Shannon MATS published 1 December 2022 Waterford MATS published 19 December 2022. Finalised, updated Greater Dublin Area Transport Strategy published January 2023. Development is underway on the updating of the Galway Metropolitan Area Transport Strategy. Draft expected to be published for consultation by Q2 2025.Avoid
82Define a governance framework for the implementation and operation of Mobility as a Service (MaaS) to encompass all transport modes nationally.Governance framework defined2024 Q4DelayedNTA submitted a position paper to DoT in May 2024 outlining the Authority’s proposed governance model for implementing an integrated Mobility as a Service (MaaS) system.Shift
87Expand shared car, bike and powered personal transporters (PPT) services at transport hubs and interchanges.Strategy for rollout of expanded shared services developed.2023 Q4A draft strategy has been prepared, taking account account of related actions in the SMP but also new actions in CAP 23/24. It is expected to be finalised in the coming months.Shift