Delay Anticipated
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 08 | Deliver fuelling/charging infrastructure to support operation of zero emission public bus fleet. | Fuelling and charging infrastructure in place for public bus fleet. | 2025 Q4 | Depot electrification works are now complete in Athlone, as is the first phase of works in two DB depots (Summerhill and Phibsboro) in Dublin and in the BÉ depot in Limerick. The second phase of works in the DB depot in Phibsboro and the BÉ depot in Limerick are almost complete, while the first phase of works in the DB depot in Harristown is well underway. Procurement of further electrification of depots in Dublin and Galway is also well advanced, and design development and procurement for other depots in Dublin, Cork and Sligo is progressing. A contract notice for an electric bus charging infrastructure framework was published on 31 March 2025. |
| 11 | Commence delivery of phase 1 of Cork Area Commuter Rail Programme. | 2024 Kent Station platform completed. 2025 Midleton double- tracking completed. | 2025 Q4 | Kent Station: Works on the new platform are complete. An official opening ceremony took place in April. Midleton Double-Tracking: Civil Engineering works are on schedule to be completed by Q1 2026, however, the new line won’t be commissioned until Q1 2027 when Cork Area Commuter Rail’s new signalling system is commissioned. |
| 13 | Transition Dublin Metropolitan PSO bus services to low/zero emission bus fleet. (Complements CAP action 268) | 50% of fleet transitioned to low/ zero emission vehicles. | 2025 Q4 | Approximately 30% of the 1,250 PSO urban buses operated by Dublin Bus and Go- Ahead Ireland are low- or zero-emission. This includes 226 diesel-electric hybrids and 153 battery-electric buses. A further 101 zero-emission battery-electric buses will be ready to join the fleet once further charging infrastructure comes onstream – this will achieve a transition rate of 38%. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 15 | Transition town and Local Link bus services to low/zero emission bus fleet. (Complements CAP actions 270 and 271) | 2022 First town transitioned to fully electric public bus service. 2025 Three additional towns transitioned to electrified bus services and 10% of Local Link services electrified. | 2025 Q4 | Athlone electric bus service launched 20 January 2023. Town services are now operated by 11 battery-electric buses. Design development for electrification of Sligo town bus service is progressing. 10 buses of the same type as deployed in Athlone, were delivered in 2024 and are intended for use in Sligo once charging infrastructure becomes available. Discussions are ongoing with Bus Éireann regarding options for electrification of further town bus services in Dundalk, Navan and Drogheda. Tender stage of competition for new single- deck battery-electric buses will commence shortly. |
| 20 | Expand rail fleet capacity. | 2023 41 additional carriages placed into passenger service. 2025 95 DART+ carriages delivered. | 2025 Q4 | All 41 Inter City Railcars i.e. carriages entered service in 2024 In respect of the 95 battery-electric Dart+ carriages, deliveries started in 2024 and will continue through to 2026. The new trains will enter passenger service following the completion of the ongoing testing and commissioning process. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 22 | Commence delivery of BusConnects network redesign in the five cities. (Complements CAP actions 239, 240) | 2022 Network of Cork and Galway services finalised. 2023 Network of Limerick and Waterford services finalised. 2025 Dublin BCNR Phases 1-11 implemented (phased implementation on an annual basis). Cork BCNR fully implemented. Galway BCNR fully implemented. | 2025 Q4 | The Cork BusConnects network was published in June 2022. Implementation planning is now ongoing which will require various infrastructure interventions across Cork City to facilitate the new routes, in addition to new fleet and depot space. The first phase is likely to be implemented from early 2026 subject to funding and availability of depot and drivers for expansion. The proposed network for Galway is in the final stages of design and works on depot electrification have commenced. A redesigned bus network for Limerick and Waterford was published in December 2023 and January 2025, respectively. Implementation planning for the new network in both cities has commenced, with the roll out of the new services to commence in 2027, subject to funding and operational readiness. Five of the eleven BusConnects Dublin network redesign phases have now been implemented. Part of Phase 6a (Route N2) was implemented at end-September and the remainder was implemented at the end of January 2025. The latest planned launch dates for the next phases are: Phase 7 (F- Spine) Q4 2025, Phase 8 (D-Spine) Q1 2026. |
| 24 | Commence delivery of MetroLink. (Complements CAP action 247) | 2022 Railway Order application submitted. 2025 MetroLink enabling works contracts commenced (subject to Government approval and planning consent). | 2025 Q4 | The Railway Order (RO) was submitted in September 2022. An oral hearing on the project was concluded 28 March 2024. A further statutory public consultation on the Railway Order, requested by An Coimisiún Pleanála (ACP), commenced August 2024 and concluded in October 2024. A decision on the RO is awaited from ACP. A procurement strategy is in development, with designers preparing designs and tender documents for advanced works contracts. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 30 | Expand greenway network establishing linkages with towns and villages in line with the strategic national cycle network. (Complements CAP action 231) | 350 km of greenway constructed or under construction. | 2025 Q4 | A total of 140km of new TII funded greenways have opened since the publication of the SMP with a further 62km currently at construction. 27km further have been constructed by the NTA, with 11km of NTA- funded Greenways under construction. |
| 34 | Develop and implement a programme of improved town bus services. | Improved town bus services implemented in Carlow, Ennis, Letterkenny, Mullingar, Portlaoise. | 2025 Q4 | Carlow’s service, launched in August 2023, has recorded 440,000 passenger journeys. Portlaoise service began in February 2025. Tender processes for new town bus services in Mullingar and Ennis are underway. Both are targeting Q4 2025 launches, pending final confirmations. In Letterkenny, public consultation is complete, with detailed planning ongoing and procurement expected in Q4 2025, subject to funding. |
| 37 | Upgrade regional rail lines. | 2022 Track renewal works completed on Ballybrophy to Limerick line. 2025 50% of programme of upgrade (and elimination) to user worked level crossings on Ballybrophy to Limerick line. 25% of track improvement works on Limerick to Waterford line. 20% of programme of upgrade (and elimination) to user worked level crossings on Limerick to Waterford line. | 2025 Q4 | The track renewal works due on the Ballybrophy to Limerick line were complete in 2022. Level crossing elimination and improvement works on the Ballybrophy to Limerick line and on the Limerick to Waterford line require additional funding and approvals in order to be progressed. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 38 | Deliver public transport corridors providing prioritised bus lanes on national radial routes to the M50. (CAP action 261) | Rollout of corridors commenced. | 2025 Q4 | The allocation for the bus priority measures scheme on the M4 between Maynooth and Leixlip in 2025 will allow civil works to be completed, but the necessary Intelligent Transport System (ITS) work is not yet in a position to proceed. With regard to the N3, work is ongoing to finalise the Option Selection Report and advance the preparation of the EIAR and planning application documentation for the N3 M50 to Clonee Bus Priority & Active Travel scheme, from Junction 2 (Snugborough) to Junction 4 (Clonee). The Option Selection Report for the M11/ N11 Bus Priority Interim Scheme from Junction 4 (Loughlinstown) to Junction 9 (Glenview) has been completed, and the project will now move to the Design and Environmental Evaluation Phase. During this phase the preparation of the EIAR and planning documentation will also be advanced. M4 Bus Priority Measures (Phase 2 – Westbound Carriageway) - Kildare County Council are advancing the development of Phase 2 of the M4 Bus Priority Measures. This is a scheme to provide bus priority and active travel links on the westbound section of the M4 between Junctions 5 and 7. The scheme is programmed to issue for development consent in Q1 2026. |
| 47 | Explore potential of road-user charging measures through the Better Road User Charging Evaluation (BRUCE) study. (CAP action 259) | Draft implementation plan published. | 2025 Q4 | A draft Alignment and Pathways report has been prepared by TII and submitted to the Department. Awaiting conclusion of the Department’s forthcoming transport strategy ‘Moving Together’ and the NTA’s GDA Demand Management Strategy as it may be necessary to update. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 78 | Deliver metropolitan area transport strategies in the cities. (Complements CAP actions 254 and 256) | 2022 Limerick Shannon Metropolitan Area Transport Strategy published. Review of Transport Strategy for the Greater Dublin Area completed, Waterford Metropolitan Area Transport Strategy published. 2023 Review of Galway Transport Strategy completed. 2025 Review of Cork Metropolitan Area Transport Strategy commenced. | 2025 Q4 | Limerick Shannon MATS - Published 1 December 2022 Waterford MATS - Published 19 December 2022. Finalised, updated Greater Dublin Area Transport Strategy published January 2023. The Galway MATS is awaiting An Coimisiún Pleanála’s determination on the re-submitted N6 Galway City Ring Road application. The NTA will then review the timeline, and publication date for the GMATS when this determination has been made. A ‘Light Rail Feasibility Study’ was published in Oct 2024. Cork update will commence later in 2025. |
| 83 | Rollout of Next Generation Ticketing (NGT) on all PSO bus services operating in Dublin. | 2023 NGT contract awarded. 2025 Implementation of first bus route with NGT. | 2025 Q4 | The NTA and Indra signed a Framework Agreement for the rollout of NGT in Q2 2024. Systems design and development underway. Work has commenced on planning for implementation of NGT in the Greater Dublin Area, with a view to rollout in the coming years. |
| 85 | Rollout Next Generation Bus Automated Vehicle Location System (AVL). | AVL system rolled out. | 2025 Q4 | Next Generation AVL is in implementation. The project commenced System Acceptance Testing (SAT) in June 2025, with a view to the first pilot going live for customers by the end of the year. |
Pages 52–57 · View in original PDF