SMP Action Status Update

SMP Action Progress to end April 2023

On Schedule 48 Actions

Complete 7 Actions

Delayed 13 Actions

At Risk of Delay 8 Actions

Ongoing 5 Actions

Figure from page 6

Figure from page 6

Complete 19%

At Risk of Delay 9%

Figure 1: Action delivery status to the end of April 2023

Full details of progress across all 91 actions may be found in Annex I. For ease of reference, the following provides a summary of the highlighted action categories in Figure 1

Page 6 · View in original PDF