Goal 4: Expand availability of sustainable mobility in regional and rural areas.

ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
30. Deliver additional walking and cycling infrastructure projects in regional and rural areas.NTADoT, LAs2030300 km of new/ upgraded walking and cycling infrastructure in regional and rural areas.Q4 2027 - 110km of new/ upgraded walking and cycling infrastructure in regional and rural areas.
31. Continue the delivery of the National Cycle Network plan (to include greenways, road space reallocation and quiet roads initiatives) to ensure establishing linkages with towns and villages.TIIDoT, NTA2030990 kms of NCN constructed.Q4 2027 - 665 kms constructed.
32. Commence reinstatement of the Western Rail Corridor between Claremorris and Athenry.NTADoT, IÉ2028Works to reinstate the Western Rail Corridor between Claremorris and Athenry commenced.Q2 2027 - Secure Approval Gate 1 consent to proceed.
33. Monitor the impact of measures on those most vulnerable to transport poverty, helping to inform future decision-making on sustainable mobility investment.DoT2030Performance against transport poverty indicators monitored and evaluated as a KPI under the SMP.Q3 2026 – Analysis undertaken, indicators identified, and methodology for recurrent data capture established.
ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
34. Complete a series of Quiet Road pilots in rural areas with suitable signage and traffic calming measures to support safe cycling.TIIDoT, LAsQ4 202710km delivered through Quiet Road pilot projects.
35. Increase the number of Park and Share sites to facilitate increased car-pooling, as delivered on the M1 Park and Share facility, with both safety and emissions benefits.TIIDoT, LAs2030Additional Park and Share facilities, in locations where there is currently unsafe informal parking taking place.Q1 2026 – TII Park and Share Strategy published. Q4 2027 – Construction commenced on at least two Park and Share facilities.
36. Complete the phased rollout and review of Connecting Ireland Rural Mobility Plan.NTADoTQ4 2028Remaining phases of Connecting Ireland implemented, subject to funding and resources. Publish annual reviews of Connecting Ireland implementation.Q3 2026 – Publish annual review.
37. Review Smart Demand Responsive Transport (SDRT) pilot programme for lessons learnt and scalability for existing DRT services.NTADoT2028Review Smart DRT pilot programme, including the feasibility of replacing the current Integrated Transport Management System on all TFI Local Link DRT services with an SDRT app.Q1 2027 – Evaluation of pilot programme.
ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
38. Advance rollout of Park and Ride Facilities under NTA’s Park and Ride Development Office.NTADoT2029At least three sites to be established.Q4 2026 – Planning consent obtained for four sites.
39. Extend programme of improved town bus services to towns across Ireland.NTADoT2030Town services introduced or improved in Naas, Newbridge, Mullingar, Ennis and Tullamore. Existing services enhanced and expanded to meet rising demand.Q1 2026 - Mullingar Town Service implemented. Q4 2026 - Ennis Town Service implemented, subject to funding and resources.
40. Continue bus stop and bus shelter programme for regional and rural services.NTADoTAnnualDeliver at least 150 additional bus shelters per year.Q4 2026 – Deliver at least 150 additional bus shelters. Q4 2027 – Deliver at least 150 additional bus shelters.