Delayed

No.ActionProposed OutputSMP DeadlineProgress
05Expand speed management measures on National, Regional and Local roads using Periodic Speed Limits at schools, Vehicle Activated Signs and Average Speed Cameras in collaboration with An Garda Síochána at appropriate high- risk locations. (RSS action 8)2024 Q4The speed limit review 2023 recommendations are being rolled out on a phased basis. Phase 1 has been completed on rural local roads on which rural speed limits are now 60kmh. Phase 2, the 30kmh urban speed limits review, is ongoing and workshops were held in Q2 2025. The introduction of 30kmh urban speed limits will be implemented by way of special speed limit bye-laws rather than a change in the default speed limit. To assist local authorities with the process of setting ‘special speed limits’ in built-up and urban areas and the attendant bye-law procedures, a working group revised the ‘Guidelines for Setting and Managing Speed Limits in Ireland’ in Q3 2025 for the purpose of setting built up and urban area speed limits. Phase 3 includes the national secondary roads speed limit default changing from 100kmh to 80kmh. Whilst the Road Traffic Act 2024 has made legislative provision for this change to take effect, this has not been commenced, as a further legislative change is required to ensure that local authorities will be permitted to set a special speed limit of 100 km/h on certain national secondary roads, where they meet the criteria specified in the Guidelines. This is being addressed by way of updated legislation to be included in the National Vehicle and Driver File (NVDF) Bill. The Bill is being finalised for publication, with progression through the Houses thereafter subject to Oireachtas scheduling. A number of average speed cameras were introduced by An Garda Síochána in 2024 in collaboration with the LAs and TII on National Roads. Additional cameras were also introduced in 2025. With regards to the Vehicle Activated Signs, these are being introduced as part of safety schemes where deemed appropriate at the discretion of the local authority.
No.ActionProposed OutputSMP DeadlineProgress
06Conduct a review of road traffic policy and legislation to prioritise the safety of walking and cycling. (RSS action 43)2023 Q4The Department has conducted some initial scoping in this regard. Implementation of the Action will involve a comprehensive review of all road traffic legislation, and can happen only in the context of consolidation of the Acts. A dedicated Division working on the consolidation of the Road Traffic Acts was established within the Department in early 2025 and is working with the Law Reform Commission on delivery of this SMP and Programme for Government commitment.
09Develop a strategy for the transition of commercial and PSO long distance bus services to low emission technologies.Strategy framework developed2023 Q4A report on Bus Éireann’s hydrogen bus pilot report has been received from BÉ and is being reviewed by NTA. A market consultation report on zero-emission ramp-accessible coaches has been completed and will inform the development of a broader strategy. Additionally, a study has been commissioned to assess the suitability of buses versus coaches for longer-distance PSO services, which will also feed into the overall strategy.
11Commence delivery of phase 1 of Cork Area Commuter Rail Programme.2024 Kent Station platform completed. 2025 Midleton double-tracking completed.2025 Q4Kent Station: Works on the new platform are complete. An official opening ceremony took place in April 2025. Midleton Double-Tracking: Civil Engineering works and track laying are now complete. However, the new line will not be fully operational until late 2027 when the new signalling system for Cork Area Commuter Rail is commissioned and the new track can be tied into the existing network.
No.ActionProposed OutputSMP DeadlineProgress
12Commence delivery of DART+ Programme. (Complements Climate Action Plan (CAP) action 246)2022 DART+ West: Railway Order application submitted. DART+ South West: Railway Order application submitted. DART+ Coastal South: First round of public consultation completed. DART+ Coastal North: First and second rounds of public consultation completed. 2023 DART+ Coastal North: Railway Order application submitted. DART+ Coastal South: Second round of public consultation. DART+ Coastal South: Railway Order application submitted.2023 Q4Funding allocated under the NDP Sectoral Investment Plan will see construction of the DART+ programme begin with DART+ West, which is planned to enter construction late 2027 and is the crucial enabler of the rest of the programme. NDP funding also allowed the commencement of Compulsory Purchase Orders for DART+ South West in February 2026. Conditional planning approval for DART+ West (July 2024), and full planning approval for DART+ South West (November 2024) and DART+ Costal North (August 2025) has been granted by An Coimisiún Pleanála. Preparation for procurement for DART+ South West and West is progressing with pre-qualification questionnaires (PQQ) notices for Design and Build works advertised in May 2025. A non-statutory public consultation was carried out by Iarnród Éireann on the Emerging Preferred Option for DART+ Coastal South, Stage 1 Bray to Greystones Capacity Enhancements, which concluded in December 2025. In terms of DART+ fleet, three orders have been placed for a total of 285 carriages/57 five-carriage sets, comprising both battery-electric and electric units. The first order for the purchase of 95 additional DART carriages (65 battery-electric and 30 electric) have started arriving in Ireland and are currently undergoing certification and safety testing. It is intended that the new battery-electric sets will initially be deployed on the Northern Commuter Line serving Dublin to/from Drogheda from Q2 2027. It is planned to deploy at least some of the second order of 90 battery-electric DART carriages to allow the commencement of the DART extension to Wicklow around 2029.
No.ActionProposed OutputSMP DeadlineProgress
13Transition Dublin Metropolitan PSO bus services to low/ zero emission bus fleet. (Complements CAP action 268)50% of fleet transitioned to low/zero emission vehicles.2025 Q4Approximately 32% of the fleet of 1250 PSO urban buses (end-2021 figure used in SMP) operated by Bus Átha Cliath-Dublin Bus and Go-Ahead Ireland are low- or zero-emission. This includes 226 diesel- electric hybrids and 169 battery-electric buses. A further 65 zero-emission battery-electric buses will be ready to join the fleet once further charging infrastructure comes onstream – this will achieve a transition rate of approximately 37%.
15Transition town and Local Link bus services to low/zero emission bus fleet. (Complements CAP actions 270 and 271)2022 First town transitioned to fully electric public bus service. 2025 Three additional towns transitioned to electrified bus services and 10% of Local Link services electrified.2025 Q4Athlone electric bus service launched 20 January 2023. Town services are now operated by 11 battery- electric buses. Design development for electrification of Sligo town bus service is progressing. 10 buses of the same type as deployed in Athlone, were delivered in 2024 and are intended for use in Sligo once charging infrastructure becomes available. Discussions are ongoing with Bus Éireann regarding options for electrification of further town bus services in Dundalk, Navan and Drogheda. Tender stage of competition for new single-deck battery-electric buses will commence shortly.
20Expand rail fleet capacity.2023 41 additional carriages placed into passenger service. 2025 95 DART+ carriages delivered.2025 Q4All 41 Inter City Railcars (i.e. carriages) entered service in 2024. In terms of DART+ fleet, three orders have been placed for a total of 285 carriages/57 five-carriage sets, comprising both battery-electric and electric units. The first order for the purchase of 95 additional DART carriages (65 battery-electric and 30 electric) have started arriving in Ireland and are currently undergoing certification and safety testing. It is intended that the new battery-electric sets will initially be deployed on the Northern Commuter Line serving Dublin to/from Drogheda from Q2 2027. It is planned to deploy at least some of the second order of 90 battery-electric DART carriages to allow the commencement of the DART extension to Wicklow around 2029.
No.ActionProposed OutputSMP DeadlineProgress
21Continue appraisal and planning for new light rail in Dublin and Cork, and consider the feasibility of light rail in Galway.2022 Emerging Preferred Route for Luas Cork identified. 2023 Planning application documentation completed for Luas Finglas. Assessment of light rail for Galway completed as part of review of Galway Transport Strategy.2023 Q4The Emerging Preferred Route (EPR) non-statutory public consultation for Luas Cork was closed and Public and stakeholder feedback has now been collated. The 1st Non-Statutory Public Consultation (NSPC) Report was published in October 2025. The project is now assessing possible alignment changes to address NSPC concerns and feedback. For Luas Finglas, the Preliminary Business Case was approved by the Government in October 2024 and Railway Order submitted to An Coimisiún Pleanála (ACP) in November 2024. It is anticipated that main construction works will commence by 2029, with some enabling works commencing prior to this. Draft Galway Transport Strategy (now known as the Galway Metropolitan Area Transport Strategy, or GMATS) was delayed while awaiting An Coimisiún Pleanála’s determination on the re-submitted N6 Galway City Ring Road application, which was published in April 2026. The NTA will now review the timeline and publication date for the GMATS.
22Commence delivery of BusConnects network redesign in the five cities. (Complements CAP actions 239, 240)2022 Network of Cork and Galway services finalised. 2023 Network of Limerick and Waterford services finalised. 2025 Dublin BCNR Phases 1-11 implemented (phased implementation on an annual basis). Cork BCNR fully implemented. Galway BCNR fully implemented.2025 Q4The Cork BusConnects network was published in June 2022 and received Government approval in October 2025 allowing for the NTA to lodge a planning application for the Sustainable Transport Corridors in 2026. Implementation planning is now ongoing which will require various infrastructure interventions across Cork City to facilitate the new routes, in addition to new fleet and depot space. The first phase is progressing, subject to funding and availability of depot and drivers for expansion. The proposed network for Galway is in the final stages of design and works on depot electrification have commenced. A redesigned bus network for Limerick and Waterford was published in December 2023 and January 2025, respectively. Implementation planning for the new network in both cities has commenced, with the roll out of the new services to commence in 2027, subject to funding and operational readiness. Seven of the eleven BusConnects Dublin network redesign phases have now been implemented. Part of Phase 6a (Route N2) was implemented at end- September 2024 and the remainder was implemented at the end of January 2025. The planned launch dates for the next phase, Phase 8 (D-Spine), of Q3 2026 is subject to funding confirmation and operational readiness.
No.ActionProposed OutputSMP DeadlineProgress
24Commence delivery of MetroLink. (Complements CAP action 247)2022 Railway Order application submitted. 2025 MetroLink enabling works contracts commenced (subject to Government approval and planning consent).2025 Q4The Railway Order (RO) was submitted in September 2022. The RO was granted by An Coimisiún Pleanála in September 2025 and became operative in January 2026. The pre-qualification process to select contractors for the main contracts commenced in February 2025.
28Develop and publish cycle network plans for all counties. (Complements CAP action 231, RSS action 176)Plans published.2023 Q4Cycle network plans have been developed for all counties, covering all regional growth centres and key towns. Public consultation on draft networks for 22 counties ran between September and November 2022. Following some amendments arising from the consultation process, finalisation of the Strategic Environmental Assessment was completed in Q3 2024 and statutory public consultation in respect of Strategic Environmental Assessment took place in Q3/Q4 2024 (https://consult.nationaltransport.ie/en/ consultation/cycleconnects). The second round of consultation is complete. Necessary environmental evaluation has been completed and, following approval, the plans will be ready for publication.
30Expand greenway network establishing linkages with towns and villages in line with the strategic national cycle network. (Complements CAP action 231)350 km of greenway constructed or under construction.2025 Q4A total of 140km of new TII-funded greenways have opened since the publication of the SMP. Approximately 30km of Greenways were delivered in 2025 with a further 20km expected to be delivered in 2026.
No.ActionProposed OutputSMP DeadlineProgress
34Develop and implement a programme of improved town bus services.Improved town bus services implemented in Carlow, Ennis, Letterkenny, Mullingar, Portlaoise.2025 Q4Carlow’s service, launched in August 2023, has recorded 440,000 passenger journeys. Portlaoise service began in February 2025. The new Mullingar town bus service launched in February 2026 The Ennis town bus service has a targeted launch date in Q4 2026. In Letterkenny, public consultation is complete, with detailed planning ongoing with implementation expected in 2027 subject to funding.
37Upgrade regional rail lines.2022 Track renewal works completed on Ballybrophy to Limerick line. 2025 50% of programme of upgrade (and elimination) to user worked level crossings on Ballybrophy to Limerick line. 25% of track improvement works on Limerick to Waterford line. 20% of programme of upgrade (and elimination) to user worked level crossings on Limerick to Waterford line.2025 Q4The track renewal works due on the Ballybrophy to Limerick line were complete in 2022. Level crossing elimination and improvement works on the Ballybrophy to Limerick line and on the Limerick to Waterford line require additional funding and approvals in order to be progressed.
No.ActionProposed OutputSMP DeadlineProgress
38Deliver public transport corridors providing prioritised bus lanes on national radial routes to the M50. (CAP action 261)Rollout of corridors commenced.2025 Q4The civil works and Intelligent Transport System (ITS) infrastructure works for the M4 Bus Priority facility are largely complete. The required legislation to commence operation is currently being progressed by the Department. It expected to commence operation within a reasonable timeframe once this legislation is implemented. With regard to the N3, work is ongoing to finalise the Option Selection Report and advance the preparation of the EIAR and planning application documentation for the N3 M50 to Clonee Bus Priority & Active Travel scheme, from Junction 2 (Snugborough) to Junction 4 (Clonee). The Option Selection Report has been finalised following a review by stakeholders and the preferred option was presented to the NTA Public Transport team and received positive feedback. The Option Selection Report for the M11/ N11 Bus Priority Interim Scheme from Junction 4 (Loughlinstown) to Junction 9 (Glenview) has been completed, and the project will now move to the Design and Environmental Evaluation Phase. During this phase the preparation of the EIAR and planning documentation will also be advanced. The design for the scheme will progress omitting bus priority southbound between Junction 6 (Fassaroe) and Junction 7 (Bray South), retaining the existing uncontrolled direct accesses in this section. The proposed improvements to Junction 7 being progressed as part of the scheme should reduce congestion significantly and will mitigate the removal of bus priority. M4 Bus Priority Measures (Phase 2 – Westbound Carriageway) - Kildare County Council are advancing the development of Phase 2 of the M4 Bus Priority Measures. This is a scheme to provide bus priority and active travel links on the westbound section of the M4 between Junctions 5 and 7. Design is ongoing with an anticipated submission for Part 8 planning approval in mid-2026, subject to completion and opening of the eastbound bus priority measures.
40Develop demand management scheme for the Greater Dublin Area.GDA demand management scheme developed and published.2023 Q4Technical work to develop a demand management scheme for the Greater Dublin Area has been completed. The scheme will be finalised in line with the national-level demand management strategy, ‘Moving Together’, which was published in March 2026.
No.ActionProposed OutputSMP DeadlineProgress
47Explore potential of road-user charging measures through the Better Road User Charging Evaluation (BRUCE) study. (CAP action 259)Draft implementation plan published.2025 Q4A draft Alignment and Pathways report has been prepared by TII and submitted to the Department. Following the publication in March 2026 of the Department’s transport strategy ‘Moving Together’, the next steps are being considered to take this work forward.
48*Promote the principle of ‘Access for All’ across sustainable mobility services through:2022 Customer service officers provided on all inter-city trains 2025 Eight additional railway stations equipped with footbridge and lifts to allow all platform access. All bus stations equipped with wheelchair accessible bus bay. Wheelchair accessible stops for lift equipped coaches provided in additional 50 towns. 100 additional low floor vehicles for regional/ inter-city coach services introduced. Roll-out of new National Journey Planner commenced. Changing Places toilets installed at three additional transport hubs.2025 Q4120 customer service officers have now been recruited by Irish Rail. Two rail stations were completed in 2022. One station in 2023 and Banteer completed in July 2024. Rathmore completed construction in August, Athy in November, as well as Maynooth and Rathmore completed in December 2025. New lift installed in Clongriffin Rail Station December 2025. Construction for the installation of lifts and footbridges commenced in Boyle and Claremorris. In total, eight rail stations are complete and four stations are in construction. There are 25 bus and train stations that require wheelchair accessible bus bays. Of these, 21 stations are completed and 4 are in the design phase to be completed in 2026 and 2027. Wheelchair accessible stops for lift equipped coaches are now provided in 51 towns. Seven towns are now served by low floor coaches. Discussion are underway with the Local Authorities to progress the remaining stops via the Bus Stop Enhancement Programme, looking at the bus stops from a wider concept. The TFI website and App features an accessibility rating for each bus stop in Ireland. 103 double deck low floor coaches were ordered and put into service by the end of 2023. 25 additional low floor double deck coaches have been put into service in 2024, exceeding the output required. All bus and coaches on TFI services are now wheelchair accessible. New Journey planner has been rolled out. Changing Places toilets installed at Heuston Station, Connolly Station and Colbert Station and planned for another two rail stations.
No.ActionProposed OutputSMP DeadlineProgress
57Review, develop and update guidelines, standards and supporting legislation to allow for a range of solutions to be developed for road space reallocation/ redesign to repurpose existing legacy car-based road design.Delivery of updates completed2023 Q4In addition to a workshop that was led by Department of Housing, Local Government and Heritage in January 2025 to consider the contents of an Advice Note that is being prepared on road space reallocation, the Department of Transport held four stakeholder events in May 2025 as part of a process to develop an updated SMP Action Plan. The views raised at those events in respect of this topic will further inform the preparation of the Advice Note. Once finalised, the Advice Note will be issued as supplementary guidance in support of DMURS. The Advice Note is expected to be completed in Q3 2026. Any supporting legislation that may be identified would be expected to form part of a broader legislative work programme under the new ‘Moving Together’ Strategy.
66Conduct a pilot (with supporting infrastructure) to examine the feasibility of introducing a ‘cyclist turning left on red’ provision. Take into account best international practice around other cycling priority measures and make recommendations. (RSS action 57)2022 Q4The amendments to the Road Traffic (Signs) Regulations and the Road Traffic (Traffic and Parking) Regulations, required to facilitate regulatory updates to the Traffic Signs Manual (TSM), have now been enacted into law. Under the Road Safety Strategy Phase 2 Action Plan, the National Transport Authority is leading on the management and delivery of the pilot scheme.
72Amend Section 17 of the Dublin Transport Authority Act 2008 to establish a National Transport Authority Advisory Council.Legislation amended2023 Q4On 17 September 2025, Government approved the priority drafting of the Dublin Transport Authority Amendment Bill 2025, amending section 44 of the Dublin Transport Authority Act 2008 (the DTA Act). A second Bill will be needed for the wider legislative amendments required to extend the NTA’s transport planning remit including around the composition of the NTA Board and the National Transport Authority Advisory Council. This will be progressed following completion of Action 75.
No.ActionProposed OutputSMP DeadlineProgress
75Extend the statutory transport planning remit of the National Transport Authority to the metropolitan areas of Cork, Galway, Limerick and Waterford.Legislation to extend remit introduced.2023 Q4On 17 September 2025, Government approved the priority drafting of the Dublin Transport Authority Amendment Bill 2025, amending section 44 of the Dublin Transport Authority Act 2008 (the DTA Act). This is a first step to enable the NTA to deliver public transport infrastructure in the regional cities, as they currently do within the GDA. Further consideration will be needed on wider legislative amendments required to extend the NTA’s remit which will be progressed in a separate wider Bill.
77Prepare and commence implementation of local transport plans for regional growth centres and key towns having regard to the Area Based Transport Assessment Guidance Note.Local transport plans for regional growth centres and key towns completed.2025 Q4Local Transport Plans (LTPs) have been completed for 4 of the 5 Regional Growth Centres with the final one, Drogheda, anticipated to be completed later this year following feedback from a public consultation to be published in Q3 2026. Additionally, LTPs have been completed for 22 of the 33 Key Towns with a further 5 underway. It is anticipated that LTPs would be commenced for 2 further Key Towns in 2026.
78Deliver metropolitan area transport strategies in the cities. (Complements CAP actions 254 and 256)2022 Limerick Shannon Metropolitan Area Transport Strategy published. Review of Transport Strategy for the Greater Dublin Area completed, Waterford Metropolitan Area Transport Strategy published. 2023 Review of Galway Transport Strategy completed. 2025 Review of Cork Metropolitan Area Transport Strategy commenced.2025 Q4Limerick Shannon MATS - Published 1 December 2022 Waterford MATS - Published 19 December 2022. Finalised, updated Greater Dublin Area Transport Strategy published January 2023. The Galway MATS was delayed pending An Coimisiún Pleanála’s determination on the re- submitted N6 Galway City Ring Road application. This determination has now been made and the NTA will now review the timeline and publication date for the GMATS. A ‘Light Rail Feasibility Study’ was published in Oct 2024. Cork update will commence later in 2026.
No.ActionProposed OutputSMP DeadlineProgress
82Define a governance framework for the implementation and operation of Mobility as a Service (MaaS) to encompass all transport modes nationally.Governance framework defined.2024 Q4The NTA submitted a paper to the Department of Transport on 28 May 2024. Work on finalising a governance structure and developing a MaaS project will commence after the Next Generation Ticketing project, which is currently underway, has been delivered.
83Rollout of Next Generation Ticketing (NGT) on all PSO bus services operating in Dublin.2023 NGT contract awarded 2025 Implementation of first bus route with NGT.2025 Q4The NTA and Indra signed a Framework Agreement for the rollout of NGT in Q2 2024. Systems design and development are underway. Work has commenced on planning for implementation of NGT in the Greater Dublin Area and a multi-phase plan has been prepared, with a view to rollout in the coming years. In Phase 1, targeted for completion by summer 2027, the new ticketing system will be developed. This will include integration with existing Leap cards so that Leap cards can continue to be used with the new system. Phase 2 will see the rollout of devices on bus and Luas services in the Greater Dublin Area, while Phase 3 will see the rollout of devices and turnstiles at all Irish Rail stations in the Greater Dublin Area. To ensure the operability of the 90-minute multi-modal fare within the Greater Dublin Area, Phase 2 and Phase 3 will go live simultaneously, with a current target date of summer 2028. From this point, public transport users in the Greater Dublin Area will be able to use contactless payment across all modes. Following this, Phase 4 will roll out ticket machines and devices on commuter buses and regional services beyond the Greater Dublin Area.
85Rollout Next Generation Bus Automated Vehicle Location System (AVL).AVL system rolled out2025 Q4Next Generation AVL is in implementation. The project commenced System Acceptance Testing (SAT) in June 2025 and the first implementation of the new system is being piloted in Waterford as of early July 2026. The NTA and supplier teams will continue to monitor performance closely throughout the coming weeks to ensure stability and identify if any improvements are required. Subject to the pilot continuing successfully the Authority will commence planning the next deployments.

Figure from page 50

Figure from page 50

Prepared by the Department of Transport gov.ie/transport

Pages 37–50 · View in original PDF