2.2 Modified

2.2 Modified

As outlined in the previous report, five of the actions set out in the SMP Action Plan – Actions 26, 31, 33, 60 and 87 – have been modified in response to changing circumstances. These actions have diverged in scope and/or direction to the extent that some of their originally envisaged outputs

For BusConnects (Action 23), all 12 corridor applications have been lodged with An

have now been superseded. However, the objectives of these actions have been addressed through a different approach.

outputs to improve accessibility in the public transport system. In total, six of the seven outputs for the action were completed before the deadline, but the target output of equipping 25 bus stations with wheelchair accessible bus bays was not fully completed by the end of 2025. Twenty-one wheelchair accessible bus bays were put in place in time, with the remaining four expected to be completed by March 2027.