6.3 Programme C - Road Networks & Road Safety
6.3 Programme C - Road Networks & Road Safety
High Level Goal: To deliver an accessible, efficient, safe and sustainable Road networks system that supports communities, households, and businesses.

Figure from page 24
Road Networks & Road Safety Indicative Annual Allocations
| Programme Area C- Road Networks & Road Safety* | |||||
|---|---|---|---|---|---|
| 2026 | 2027 | 2028 | 2029 | 2030 | |
| €1.6bn | €1.6bn | €1.7bn | €2.1bn | €2.7bn |
*All funding is indicative and subject to annual Estimates process; rounding may affect totals.
Investment Strategies
Roads Network Investment in Ireland’s national road network is a cornerstone of the Road Safety Strategy 2021–2030, which aims to halve road deaths and serious injuries by 2030. This is further recognised in a number of priority actions in the Phase 2 Action 2025-2027 under the Strategy, approved by Government earlier in 2025.
National Roads 2040 (NR2040) is a long-term investment framework for the maintenance, development, and management of Ireland’s National Roads network. This aims to enable the delivery of Project Ireland 2040 (National Planning Framework), support the realisation of several National Strategic Outcomes and align with NIFTI and government policy.
Investment in the Regional and Local Roads Programme is guided by the TAF, and the Department works in collaboration with local authorities to deliver the programme.
Decarbonising Transport Strategies for the decarbonisation of road transport are set out in the Climate Action Plan, which sets a target of 30% of the private car fleet being electric by 2030. The 2025 interim target of 195,000 EVs on the road has been met. In accordance with this strategy, funding is provided to bridge the purchase price gap between ICEs and EVs and so incentivise the uptake of zero emission vehicles.
Funding is also provided to support the adoption of home charging and depot charging solutions, as these provide a low cost and convenient charging option for EV drivers and place the least demand on the constrained electricity grid.
ZEVI has also developed strategies for a planned roll out of national EV charging infrastructure, with plans for delivery at national road and at regional and local level. Investment in EV infrastructure is vital to ensuring consumer confidence and encouraging widespread adoption. Incentives for public charging infrastructure not only complement significant private sector investment but enable a just transition across the country. While private operators may invest in more commercially viable locations, government supports can ensure that rural, regional, and community areas are equally as accessible, to ensure a charging network that meets the needs of all citizens across Ireland.
HDV For heavy duty vehicles, targeted grants are essential to address both technological and cost barriers. HDVs contribute approximately 20% of transport emissions, and supporting their transition to zeroemission will be significant to achieving Ireland’s overall emissions goals. Maintaining schemes like the ZEHDV Grant, ZEHDV-I/P Grant, and the Fleet Assessment Grant, supports operator’s transition and the delivery of infrastructure required along key routes. ZEVI is developing a framework for the decarbonisation of the HDV fleet, in collaboration with industry, to demonstrate a pathway for the electrification of this more challenging sector.
Programme Summary
Our road network is approximately 102,000km in length. Of this, 5,300km consists of national roads and motorways, with the remainder forming the regional and local road network. Taken together, this network is a critical national asset, facilitating the movement of people and goods across the country. It facilitates business, education, tourism, healthcare, agriculture, and the provision of critical services and activities.
The NDP funding for roads is allocated by the Department and its agency TII to Local Authorities in line with the Department’s NIFTI intervention hierarchy of Maintain, Optimise, Improve, and New. This approach involves prioritising investment in the protection and renewal of existing assets before investing in new ones, on economic, safety, and environmental grounds.
Under Maintain, key road programmes are funded, including the funding of the protection and renewal of the national, regional, and local road network. This enables the maintenance of the road network to a safe standard, maintenance of motorway network, management of seasonal and climate impacts, and ensuring roads comply with the Pavement Condition Survey Indicator (PCSI) metrics.
In terms of Optimise, this NDP funding will support TII and Local Authorities in delivering additional Park and Ride facilities, the roll out of EV charging infrastructure to support the decarbonisation of the network, delivery of adaptation measures on our road network response to the climate emergency, and support the deployment of Intelligent Transport Systems.
With regard to Improve, there will be targeted road safety improvements such as removing dangerous bends, junction improvements, and a focus on improved road signage and line markings. Upgraded strategic urban roads and bypasses will be delivered improving access to towns and the public realm space, while, in addition, bus priority measures will be developed on the road network. There will also be
continued investment in Active Travel improvements along both our national and regional road network, including wider footpaths and segregated cycleways. Upgraded strategic urban roads and bypasses will be delivered, improving access to towns and the public realm space, while, in addition, bus priority measures will be developed on the road network.
This NDP will see the construction of many new national and regional roads across the state, with many others commencing construction or being advanced through the planning and procurement process. This funding will allow TII and the Local Authorities to complete schemes such as the M28 Cork to Ringaskiddy, N21/69 Limerick to Foynes (incl. Adare Bypass), and the N5 Ballaghaderreen to Scramoge projects, as well as commencing construction on schemes such as the Donegal TEN-T Project, the N24 Cahir to Limerick Junction, and the Slane Bypass among others.
Furthermore, on the regional and local road networks, projects such as Coonagh Knockalisheen Distributor Road in Limerick, Eastern Garvoge Bridge and Approach Roads in Sligo and the Great Island Connectivity Scheme (R624 Cobh Road) will continue / commence construction. In addition, and as summarised in the Appendix, funding under the NDP will also ensure the continued development of a pipeline of projects for future construction.
Investment under the roads programme will also improve connections to Dublin Airport from the north and west, complementing improved public transport infrastructure and services to / from the airport.
The Programme for Government places strong emphasis on decarbonising transport as part of its climate commitments. As referenced earlier, ZEVI is a dedicated Office within the Department of Transport, charged with supporting consumers, the public sector, and businesses to continue to make the switch to zero emission vehicles. The Office plays a strategic role in supporting the NDP by accelerating Ireland’s transition to reducing emissions and leads on the delivery of Ireland’s ambitious targets under the Climate Action Plan 2023 to have an expected 30% of our private car fleet switched to electric by 2030.
The ‘Avoid, Shift, Improve’ approach presents a framework for structuring policy measures within ZEVI Climate Action in the Transport sector. As part of the ‘Improve’ element, electrification has a key role in decarbonising transport, accounting for nearly two thirds of transport mitigation measures under the Climate Action Plan. Electric vehicles have a lead role to play in transforming the Irish transport system into one that is clean, green, and sustainable. This improved system will support communities and economic growth as we move towards a net zero carbon future.
This NDP will see EV charging infrastructure deployed along our National Primary and Secondary roads, as well as the delivery of a public Regional and Local EV recharging network at destination and neighbourhood areas through Local Authorities to maximise electric mobility transition for all citizens, as well as supports for citizens and businesses to switch to electric vehicles .
Delivery Structures
National Road projects are delivered by TII as the day-to-day Approving Authority working in consultation with relevant local authorities as the Sponsoring Agencies. The Department sets policy and funds the roads programme while retaining oversight of TII. The Governance arrangements include quarterly Governance meetings, quarterly National Roads and Greenways Monitoring Group meetings, and regular ongoing communications between the Department, TII, and Local Authorities.
The Regional and Local Roads Programme has well-established governance and delivery structures, with the Department of Transport acting as the Approving Authority working in consultation with the road (local) authority sector as the Sponsoring Agencies. The Department is in regular contact with Local Authorities and conducts frequent operational meetings with Local Authority staff and engineers.
For decarbonisation of road transport, vehicle schemes are administered by the SEAI, TII, and the NTA, with the Department as Approving Authority. Infrastructure delivery is through the SEAI, Local Authorities, and TII, with the Department and TII acting as Approving Authorities. As part of a strategic realignment to enhance the delivery of Ireland’s sustainable transport objectives, infrastructure functions of the ZEVI office are transitioning to TII.
This move reflects the growing integration of EV policy with broader transport infrastructure planning and delivery. The transition aims to streamline the implementation of certain EV grants, recharging infrastructure, alternative fuels data, and public engagement initiatives, ensuring they are closely aligned with national transport strategies and infrastructure development.
The transition will also support more cohesive planning across urban and regional mobility, helping accelerate the shift to zero-emission transport in line with climate targets. Governance arrangements, vehicle grants, certain data functions, and some communications functions will remain in the Department, with Regional and Local plan related infrastructure work transferring to TII in 2026. New governance mechanisms are being established as part of the transition working groups key activities.
List of of Major National Roads Projects (>€200m) Scheduled to Commence Construction / Procurement by 2030 2
| Project | Approving Authority | Sponsoring Agency | Current Stage of Project Lifecycle | Next Approval Gate | Procurement Timeline * | Construction Timeline | Successful Tenderer | Cost Range |
|---|---|---|---|---|---|---|---|---|
| Donegal TEN-T Project | TII | Donegal County Council | Project Design, Planning & Procurement Strategy | AG2 | By 2027 | Commence By 2028 | Not yet awarded | €500m- €1bn |
| N2 Ardee to South of Castleblayney | TII | Monaghan County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2030 | 2030+ | Not yet awarded | €250m- €500m |
| N2 Clontibret to the Border | TII | Monaghan County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | Commence By 2030 | Not yet awarded | €250m- €500m |
| N2 Slane Bypass | TII | Meath County Council | Project Design, Planning & Procurement Strategy | AG2 | By 2027 | Commence By 2028 | Not yet awarded | €100m- €250m |
| N3 Virginia Bypass | TII | Cavan County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2028 | Commence By 2029 | Not yet awarded | €250m- €500m |
| N4 Carrick on Shannon Bypass and Traffic Management Project | TII | Leitrim County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2027 | Commence By 2028 | Not yet awarded | €250m- €500m |
Progression of all individual projects remains subject to compliance with the Infrastructure Guidelines, statutory planning and procurement requirements, as relevant.
| Project | Approving Authority | Sponsoring Agency | Current Stage of Project Lifecycle | Next Approval Gate | Procurement Timeline * | Construction Timeline | Successful Tenderer | Cost Range |
|---|---|---|---|---|---|---|---|---|
| M4 Maynooth to Leixlip | TII | Kildare County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | Commence By 2030 | Not yet awarded | €100m- €250m |
| N4 Mullingar to Longford | TII | Westmeath County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2030 | 2030+ | Not yet awarded | €500m- €1bn |
| N5 Ballaghaderreen to Scramoge | TII | Roscommon County Council | Implementation | N/A | N/A | Completion by 2027 | Wills Bros Ltd | €250m- €500m |
| N6 Galway City Ring Road | TII | Galway County Council | Project Design, Planning & Procurement Strategy | AG2 | By 2028 | Commence By 2029 | Not yet awarded | €1bn+ |
| N11/25 Oilgate to Rosslare | TII | Wexford County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | Commence By 2030 | Not yet awarded | €250m- €500m |
| N17 Knock to Collooney | TII | Sligo County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | 2030+ | Not yet awarded | €500m- €1bn |
| N/M20 Cork to Limerick | TII | Limerick City and County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | 2030+ | Not yet awarded | €1bn+ |
| N21 Abbeyfeale Relief Road | TII | Limerick City and County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | Commence By 2030 | Not yet awarded | €100m- €250m |
| N21/69 Limerick to Foynes (inc Adare Bypass) | TII | Limerick City and County Council | Project Design, Planning & Procurement Strategy | AG2 | By 2027 | Adare Bypass element completion due in 2027 | Not yet awarded | €500m- €1bn |
| N21 Newcastle West Relief Road | TII | Limerick City and County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2028 | Commence by 2029 | Not yet awarded | €100m- €250m |
| N22 Farranfore to Killarney | TII | Kerry County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | Commence by 2030 | Not yet awarded | €250m- €500m |
| N24 Cahir to Limerick Junction | TII | Tipperary County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | 2030+ | Not yet awarded | €500m- €1bn |
| N25 Midleton to Youghal (Castlemartyr and Killeagh Bypasses) | TII | Cork County Council | Strategic Assessment & Preliminary Business Case | AG1 | By 2029 | Commence By 2030 | Not yet awarded | €100m- €250m |
| M28 Cork to Ringaskiddy | TII | Cork County Council | Implementation | N/A | N/A | Completion By 2028 | BAM Civil Ltd | €250m- €500m |
List of Strategic Regional Road Projects Scheduled to Commence Construction by 2030 3
| Project | Approving Authority | Sponsoring Agency | Current Stage of Project Lifecycle | Next Approval Gate | Procurement Timeline | Construction Timeline | Successful Tenderer | Cost Range |
|---|---|---|---|---|---|---|---|---|
| Athenry Relief Road, section 3 and 5 | DoT | Galway County Council | Implementation | N/A | N/A | Completion due 2026 | Tower Civil Engineering | €5m- €10m |
| Coonagh to Knockalisheen Distributor Road | DoT | Limerick City & County Council | Implementation | N/A | N/A | Completion due 2027 | Roadbridge Ltd | €50m- €100m |
| Eastern Garavoge Bridge and Approach Roads | DoT | Sligo County Council | Strategic Assessment & Preliminary Business Case | AG2 | N/A | Commence by 2026 | RPS / Hewson | €20m- €50m |
| Great Island Connectivity Scheme (R624 Cobh Road) | DoT | Cork County Council | Strategic Assessment & Preliminary Business Case | AG1 | Procurement by 2029 | Commence by 2030 | Not yet awarded | €100m- €250m |
| Killarney Strategic Links Project | DoT | Kerry County Council | Strategic Assessment & Preliminary Business Case | AG1 | Procurement by 2026 | Commence by 2027 | Not yet awarded | €10m- €20m |
| R188 Rathkenny East West Road (Cavan) | DoT | Cavan County Council | Strategic Assessment & Preliminary Business Case | AG1 | Procurement by 2028 | Commence by 2029 | Not yet awarded | €20m- €50m |
| R263 Fintra Bridge and Road Realignment | DoT | Donegal County Council | Implementation | N/A | N/A | Completion due 2026 | BAM Civil Ltd | €10m- €20m |
| R498 Latteragh Upgrade | DoT | Tipperary County Council | Final Business Case | AG3 | N/A | Commence by 2025 | Wills Bros Ltd | €20m- €50m |
| Thurles Inner Relief Road | DoT | Tipperary County Council | Strategic Assessment & Preliminary Business Case | AG1 | Procurement by 2026 | Commence by 2027 | Not yet awarded | €10m- €20m |
| Tralee Northern Relief Road | DoT | Kerry County Council | Implementation | N/A | N/A | Phase 1 completion due 2026 | Alan O Connell Developments Limited & TBC | €20m- €50m |
Pages 24–29 · View in original PDF