7.2Implementation Cost

High-level cost forecasts were developed to provide an indicative range for delivering the entire NCN. It was not possible to develop a detailed forecast of costs as neither the specific routes nor the link types are determined at this stage. As such, the high-level cost forecasts are based on a number of assumptions, as follows:

Indicative costs per km were based on the best available information in 2022 and does not include inflation or fluctuations to underlying inputs (e.g., labour, materials). The costs applied are presented in the table below.

To inform the distribution of cost across implementation phases, it was assumed that 10% of costs will be allocated to the planning and design phases and the remaining 90% to construction.

Lengths are based on the centreline of NCN corridors and the assessment of known existing and planned cycle infrastructure.

To ensure the forecasts cover a range of potential infrastructure requirements, costs for two scenarios have been developed as follows:

Scenario 1.Provides a high level of segregated infrastructure using off-road cycleways and the

remainder on shared / ”quiet” roads.

Scenario 2.Provides a low level of segregated infrastructure using off-road cycleways and the

remainder on shared / ”quiet” roads.

National Cycle Network Plan

Table 7.1: Indicative Cost per km by Infrastructure Type

Infrastructure TypeCost per km
Cycle Trail (Greenway)€ 1,000,000
Off-road Cycle Way€ 490,000
Standard Cycle Track€ 270,000
Quiet Road€ 170,000
Signage & amenities only (for existing cycle infrastructure)€ 75,000

Based on these cost assumptions, the estimated total cost of delivering the NCN is €1.49bn to €1.91bn, based on 2022 figures with no allowance for inflation. Approximately €30m will be required to upgrade the existing infrastructure to include the NCN design standard, especially signage. The cost of planned greenways is €940m while the remaining infrastructure will cost between €520m and €940m, depending on the type of infrastructure to be delivered.

Table 7.2: Estimated Costs for Infrastructure Scenarios (€M)

Current StatusEstimated Cost (€M)
Scenario 1Scenario 2
Existing infrastructure (resigning costs)€30€30
Proposed / planned greenways€940€940
Remaining (i.e., neither existing cycle infrastructure nor proposed / planned greenway)€940€520
Total (€M)€1,910€1,490