9 Sligo to

Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
River SAC,Union Wood SAC,Killala Bay/Moy Estuary SAC,Turloughmore (Sligo) SAC,Lough Hoe Bog SAC, Ballysadare Bay SPA,Cummeen Strand SPAlocated lie within 2km of Ballysadare Bay SPA and Cummeen Strand SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. At Ballisodare and again at Collooney the entire 4km corridorconstruction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering the crossing of the Unshin River should be as follows: 1. Where feasible the crossing will be made using existing road bridges; 2. Where engineering works to a road bridge would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or salmon population; 3. If a new bridge crossing the Unshin River SAC is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC boundary and/or must involve no loss of qualifying SAC habitat; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
traverses the Unshin River SAC. The SAC is designated for its water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho- Batrachion vegetation, its semi-natural dry grasslands and scrubland facies on calcareous substrates, its Molinia meadows on calcareous, peaty or clayey- silt-laden soils, its alluvial forests with Alnus glutinosa and Fraxinus excelsior and its populations ofrequire a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding salmon and otter will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of either species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the Unshin River is required but it is not possible to deliver such a crossing over the SAC without an adverse effect on site integrity, the Corridor should be revised (such as to not to connect to Sligo) to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
salmon and otter. It would not be possible to make the connection to Sligo from the south without crossing the Unshin River SAC due to the length of the river.
1 0Ballina to CastlebarRiver Moy SAC,Killala Bay/Moy Estuary SAC, Lough Conn and Lough Cullin SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required)The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Parts of the 4km corridor lie within 2km ofworks are consented. The approach to delivering the crossing of the River Moy should be as follows: 1. Where feasible the crossing will be made using one of existing road bridges across the River Moy; 2. Where engineering works to a road bridge would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or white-clawed crayfish, salmon or lamprey populations; 3. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC/SPA boundaries and/or must involve no loss of qualifying SAC habitat or supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding SPA birds, salmon, lamprey and otter will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of either species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Lough Conn and Lough Cullin SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. West of Foxford the entire 4km corridor traverses the River Moy SAC/ Lough Conn and Lough Cullin SPA. The SAC is designated fordemonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the River Moy SAC or Lough Conn and Lough Cullin SPA would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to make the 20km eastwards detour to avoid the River Moy to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
its lowland hay meadows, active raised bogs, degraded raised bogs still capable of natural regeneration, depressions on peat substrates of the Rhynchosporion , alkaline fens, old sessile oak woods with Ilex and Blechnum in the British Isles, alluvial forests with Alnus glutinosa and Fraxinus excelsior and its populations of white clawed crayfish, sea lamprey, brook lamprey, salmon and otter. It would be
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
possible to divert around the SPA but due to the length and large area covered by the River Moy it would not be possible to deliver this corridor without a crossing of the River Moy SAC without a c. 20km detour and back.
1 1Westport to CastlebarClew Bay Complex SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and airNo constraints or mitigation needed
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). The
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
western-most part of the corridor at Westport lies within 2km of Clew Bay Complex SAC. However, this constitutes an area of open water that is a very small part of the overall corridor and this SAC is not designated for mobile species that would use the land around the cycle route.
1 2Galway to CastlebarLough Corrib SAC,Galway Bay Complex SAC,River Moy SAC,Balla Turlough SAC,Inner Galway Bay SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise andThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, orpotential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering the River Moy crossing should be as follows: 1. Where feasible the crossing will be made using one of existing road bridges across the River Moy; 2. Where engineering works to a road bridge would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or white-clawed crayfish, salmon or lamprey populations; 3. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC boundary and/or must involve no loss of qualifying SAC habitat; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding salmon, lamprey and
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
using standard mitigation methods). The southern-most part of 4km corridor within which the final cycle route will be located lies within 2km of Inner Galway Bay SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. Inotter will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of either species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the River Moy SAC would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to make the 20km eastwards detour to avoid the River Moy to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the vicinity of Lakeland Lower the entire 4km corridor traverses the River Moy SAC. Due to the length and large area covered by the River Moy it would not be possible to deliver this corridor without a crossing of the River Moy SAC without a c. 20km detour and back.
1 3Castlebar to LongfordRiver Moy SAC,Lough Ree SAC,Balla Turlough SAC,Cloonchambers Bog SAC,Brown Bog SAC,Corliskea/Trien/Cloonfelliv Bog SAC,Lough Forbes Complex SAC, Corbo Bog SAC, Ballykenny- Fisherstown Bog SPAThe southern- most part of 4km lies within 2km of Lough Ree SPA. Since this site is designated for mobile species that may make use of habitatThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. In the vicinity of Lakeland Lower the entire 4km corridor for both routes traverses the River Moy SAC. Due to the length and large area covered by the River Moy it would not be possible to deliver this corridor without a crossing of thepotential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering the River Moy crossing will be as follows: 1. Where feasible the crossing will be made using one of existing road bridges across the River Moy; 2. Where engineering works to a road bridge would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or white-clawed crayfish, salmon or lamprey populations; 3. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC boundary and/or must involve no loss of qualifying SAC habitat; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding salmon, lamprey and
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
River Moy SAC without a c. 20km detour and back.otter will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of either species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the River Moy SAC would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to make the 20km eastwards detour to avoid the River Moy to demonstrate no adverse effect on site integrity.
1 4Roscommon to AthloneLough Ree SAC, River Shannon Callows SAC, Lough Ree SPA, Middle Shannon Callows SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise ifGiven the width of the 4km corridor it is possible to deliver most of the final cycle route without any direct effects on European sites. The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). The southern-most part of 4km corridor lies within 2km ofrelevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Lough Ree SPA and Middle Shannon Callows SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
1 5Athlone to LongfordLough Ree SAC,River Shannon Callows SAC,Brown Bog SAC,Lough Forbes Complex SAC, Corbo Bog SAC, Lough Ree SPA,Ballykenny-Fisherstown Bog SPA,Middle Shannon Callows SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoidedThe final route alignment should avoid any new construction within 200m of any European sites where possible and within 200m of any European sites there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure insignificant air pollution impacts on sensitive habitats. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the most constrained sections, or using standard mitigation methods). Parts of the 4km corridor lies within 2km of Lough Ree SPA, Ballykenny- Fisherstown Bog SPA and Middle Shannon Callows SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
functionally- linked land for SPA birds outside the SPA boundary
1 6Longford to MullingarLough Ennell SAC, Lough Ennell SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routingThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Lough Ennell SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary
1 7Athlone to MullingarLough Ennell SAC,Carn Park Bog SAC,Crosswood Bog SAC,Lough Ree SAC,River Shannon Callows SAC,Lough Ree SPA,Lough Ennell SPA,Middle Shannon Callows SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran withinThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Lough Ree SPA, Lough Ennell SPA, Middleprovided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Shannon Callows SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary
1 8Athlone to TulamoreCharleville Wood SAC,Lough Ree SAC,River Shannon Callows SAC,Moyclare Bog SAC,Mongan Bog SAC,Pilgrim’s Road Esker SAC,Crosswood Bog SAC,Fin Lough (Offaly) SAC,River Suck Callows SPA,Lough Ree SPA,Mongan Bog SPA,Middle Shannon Callows SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore,The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrainednew construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of four SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Suck Callows SPA,Lough Ree SPA,Mongan Bog SPA and Middle Shannon Callows SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally-
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
linked land for SPA birds outside the SPA boundary.
1 9Limerick to PortlaoiseSlieve Bloom Mountains SAC,Lower River Shannon SAC,River Barrow And River Nore SAC,Slieve Bloom Mountains SPA,River Shannon and River Fergus Estuaries SPA,Lough Derg (Shannon) SPAPart of the 4km corridor lies within 2km of Slieve Bloom Mountains SPA, River Shannon and River Fergus Estuaries SPA and Lough Derg (Shannon) SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land forThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering the crossing of the Slieve Bloom Mountains and River Nore should be as follows: 1. Where feasible the corridor will follow the existing road through the SAC/SPA; 2. Where engineering works to the road would be required to render it suitable, there must be no loss of SAC habitat and an assessment would be required to ensure there was no loss of functionally-linked habitat that might affect the ability of the SPA to support its hen harrier population. Construction must be timed to avoid the sensitive season for hen harrier. 3. Where engineering works to a road bridge across the River Barrow & River Nore SAC
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SPA birds outside the SPA boundary. Between Ballyduff and Carrowreagh the entire 4km corridor lies within Slieve Bloom Mountains SPA for at least 5km and it also passes through the SAC at Lacka. At Lacka the 4km corridor also crosses the River Barrow And River Nore SAC. The Slieve Bloom Mountains SAC is designated for its wet heaths with Erica tetralix,would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. They must be situated so that no loss of SAC plant species would arise. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or Desmoulin’s Whorl Snail, Freshwater Pearl Mussel, White-clawed Crayfish, Sea Lamprey, Brook Lamprey, River Lamprey, Twaite Shad, Salmon, Otter, Killarney Fern and Nore Pearl Mussel populations; 4. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC/SPA boundaries and/or must involve no loss of qualifying SAC habitat or supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding hen harrier, otter and qualifying fish species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that any improvements to the existing road through
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
blanket bogs and alluvial forests with Alnus glutinosa and Fraxinus excelsior. The SPA is designated for its hen harrier population. The River Barrow and Nore SAC is designated for its estuaries, mudflats and sandflats not covered by seawater at low tide, reefs, Salicornia and other annuals colonising mud and sand, Atlantic salt meadows, Mediterranean salt meadows, Water courses of plain to montane levelsthe Slieve Bloom Mountains SAC/SPA or a new crossing of the River Nore would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to end before Portlaoise to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
with the Ranunculion fluitantis and Callitricho- Batrachion vegetation, European dry heaths, Hydrophilous tall herb fringe communities of plains and of the montane to alpine levels, Petrifying springs with tufa formation, Old sessile oak woods with Ilex and Blechnum in the British Isles, Alluvial forests with Alnus glutinosa and Fraxinus excelsior, Desmoulin’s Whorl Snail, Freshwater Pearl Mussel,
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
White-clawed Crayfish, Sea Lamprey, Brook Lamprey, River Lamprey, Twaite Shad, Salmon, Otter, Killarney Fern and Nore Pearl Mussel. There is no way to make the connection to Portlaoise without traversing the River Barrow & River Nore SAC and/or the River Nore SPA.
2 0Limerick to AthloneLower River Shannon SAC,Lough Derg, North-east Shore SAC,Lough Ree SAC,River Shannon Callows SAC,Kilcarren- Firville Bog SAC,Mongan Bog SAC,Pilgrim’s Road Esker SAC,Crosswood Bog SAC,Fin Lough (Offaly) SAC,Redwood Bog SAC,River Shannon and RiverPart of the 4km corridor lies within 2km of River Shannon and River Fergus Estuaries SPA, River Suck Callows SPA, Lough Ree SPA,The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Fergus Estuaries SPA,River Suck Callows SPA,Lough Ree SPA,Lough Derg (Shannon) SPA,River Little Brosna Callows SPA,Mongan Bog SPA,Middle Shannon Callows SPALough Derg (Shannon) SPA, River Little Brosna Callows SPA, Mongan Bog SPA and Middle Shannon Callows SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. At Templedew the entire 4kmwithin 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering the crossing of the River Shannon should be as follows: 1. Where feasible the crossing will be made one of the existing road bridges across the River Shannon; 2. Where engineering works to a road bridge would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks; 3. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC/SPA boundaries and/or must involve no loss of qualifying SAC habitat or supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding SPA birds and otter will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of either species. e. Water quality protection measures will be required as well as a hydrological study to
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
corridor crosses the River Shannon Callows SAC and Middle Shannon Callows SPA. The SAC is designated for Molinia meadows on calcareous, peaty or clayey- silt-laden soils, lowland hay meadows, alkaline fens, limestone pavements, alluvial forests with Alnus glutinosa and Fraxinus excelsior and its population of otter. The SPA is designated for whooper swan, wigeon, corncrake,confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the River Shannon would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to end south of the River Shannon to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
golden plover, lapwing, back- tailed godwit, black-headed gull and its wetland and waterbird assemblage. There is no way to make the connection to Athlone without crossing the River Shannon and thus traversing the SAC and/or SPA or crossing the River Suck Callows SPA.
2 1Galway to AthloneLough Corrib SAC,Galway Bay Complex SAC,Glenloughaun Esker SAC,Lough Ree SAC,River Shannon Callows SAC,Rahasane Turlough SAC,Lough Rea SAC, River Suck CallowaAt Ballinasloe the entire 4km corridor traverses the River Suck Callows SPA. The SPA is designated forThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no air pollution impacts on sensitive habitats. The approach to delivering the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
its population of whooper swan, wigeon, golden plover, lapwing, Greenland white fronted goose and its wetland and waterbird assemblage. There is no way to make the connection to Athlone without crossing the River Suck Callows SPA or crossing the River Shannon (and its European sites).River Suck crossing should be as follows: 1. Where feasible the crossing will be made one of the existing road bridges across the River Suck; 2. Where engineering works to a road bridge would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity,; 3. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SPA boundaries and/or must involve no loss of supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure that no damage to banks occurs; c. A noise impact assessment of bridge construction regarding SPA birds will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population. d. Water quality protection measures will be required. e. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the River Suck would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to end south of the River Suck to demonstrate no adverse effect on site integrity.
2 2Galway to EnnisLough Corrib SAC,Moyree River System SAC,Ballyallia Lake SAC,East Burren Complex SAC,Galway Bay Complex SAC,Coole-Garryland Complex SAC,Lough Fingall ComplexThe 4km corridor is sufficiently wide that direct impacts on any European sitesThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SAC,Lower River Shannon SAC,Ballyogan Lough SAC,Caherglassaun Turlough SAC,Old Farm Buildings, Ballymacrogan SAC,Dromore Woods And Loughs SAC,Termon Lough SAC,Coole-Garryland SPA,Inner Galway Bay SPA,Cregganna Marsh SPA,Ballyallia Lough SPAcan be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating newproject level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Coole- Garryland SPA, Inner Galway Bay SPA, Cregganna Marsh SPA and Ballyallia Lough SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
affect functionally- linked land for SPA birds outside the SPA boundary.
2 3Ennis to LimerickBallyallia Lake SAC,Lower River Shannon SAC,Newhall and Edenvale Complex SAC,Lough Gash Turlough SAC,River Shannon and River Fergus Estuaries SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through eitherThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Shannon and River Fergus Estuaries SPA. Since this site is designated for mobile species that may make
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
2 4Shannon to Ennis/Limeric kLower River Shannon SAC,River Shannon and River Fergus Estuaries SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required)The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km ofhabitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
River Shannon and River Fergus Estuaries SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
2 5Tralee to LimerickTralee Bay And Magharees Peninsula, West To Cloghane SAC,Askeaton Fen Complex SAC,Lower River Shannon SAC,Moanveanlagh Bog SAC,River Shannon and River Fergus Estuaries SPA,Tralee Bay Complex SPA,Stack’s toPart of the 4km corridor lies within 2km of River Shannon and River Fergus Estuaries SPA, Tralee Bay Complex SPA,The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Mullaghareirk Mountains, West Limerick Hills and Mount Eagle SPAStack’s to Mullaghareirk Mountains and West Limerick Hills and Mount Eagle SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. At Ballynageragh, Ballyhorgan East and Shanbally the entire 4km corridorsignificant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering this corridor should be as follows: 1. Where feasible the corridor will follow existing roads through the SPA and across the SAC river; 2. Where engineering works to the road would be required to render it suitable, an assessment would be required to ensure there was no loss of functionally-linked habitat that might affect the ability of the SPA to support its hen harrier population. Construction must be timed to avoid the sensitive season for hen harrier. 3. Where engineering works to a road bridge across the Lower River Shannon SAC would be required to render it suitable, and must not hinder potential for otter passage along the riverbanks. They must be situated so that no loss of SAC plant species would arise. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or qualifying fish and dolphin populations; 4. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC/SPA boundaries and/or must involve no loss of qualifying SAC habitat or supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
traverses the Lower River Shannon SAC. The SAC is designated for sandbanks which are slightly covered by sea water all the time, estuaries, mudflats and sandflats not covered by seawater at low tide, coastal lagoons, large shallow inlets and bays, reefs, perennial vegetation of stony banks, vegetated sea cliffs of the Atlantic and Baltic coasts, Salicornia and other annuals colonising mud and sand,the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding hen harrier, otter and qualifying fish and dolphin species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that any improvements to existing roads through the Stack’s to Mullaghareirk Mountains, West Limerick Hills and Mount Eagle SPA, or a new crossing of the River Shannon, would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to end before Limerick to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Atlantic salt meadows, Mediterranean salt meadows, water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho- Batrachion vegetation, Molinia meadows on calcareous, peaty or clayey- silt-laden soils, alluvial forests with Alnus glutinosa and Fraxinus excelsior and its populations of freshwater pearl mussel, sea lamprey, brook lamprey, river lamprey, salmon, otter
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
and bottlenose dolphin. Between Doonakenna and Glendarragh much of the 4km corridor lies across Stack’s to Mullaghareirk Mountains, West Limerick Hills and Mount Eagle SPA. The SPA is designated for its population of hen harrier. It would be possible to make the connection to Limerick without traversing the SPA by moving the corridor south of the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SPA but it is not possible to make the connection to Limerick without traversing either the Lower River Shannon SAC or the Blackwater River SAC.
2 6Newcastle West to Tralee/ LimerickN/AN/ANo constraints or mitigation needed
2 7Cork to TraleeSt. Gobnet’s Wood SAC,Killarney National Park, Macgillycuddy’s Reeks And Caragh River Catchment SAC,Tralee Bay And Magharees Peninsula, West To Cloghane SAC,Ballyseedy Wood SAC,Sheheree (Ardagh) Bog SAC,The Gearagh SAC,Slieve Mish Mountains SAC,Castlemaine Harbour SAC,Tralee Bay Complex SPA,Mullaghanish to Musheramore MountainsThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impactsThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SPA,Killarney National Park SPA,The Gearagh SPA(if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4kmpotential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
corridor lies within 2km of Tralee Bay Complex SPA, Mullaghanish to Musheramore Mountains SPA ,Killarney National Park SPA and the Gearagh SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
2 8Cork to BandonCork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections ofThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
affect functionally- linked land for SPA birds outside the SPA boundary.
2 9Cork to KinsaleCork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through eitherThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
3 0Cork to Cork airportCork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final routeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods).Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since thisof the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
3 1Cork airport to CarrigalineCork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbanceThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigationbirds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
3 2Port of Cork to CarrigalineCork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sitesThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating newproject level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
3 3Cork to Port of CorkSt. Gobnet’s Wood SAC,Cork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections ofThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
affect functionally- linked land for SPA birds outside the SPA boundary.
3 4Cobh to MidletonGreat Island Channel SAC,Cork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through eitherThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
3 5Cork to CobhGreat Island Channel SAC,Cork Harbour SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final routeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Cork Harbour SPA. Since thisof the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
3 6Cork to WaterfordBlackwater River (Cork/Waterford) SAC,Great Island Channel SAC,Lower River Suir SAC,Glendine Wood SAC,Ballymacoda (Clonpriest and Pillmore) SAC,Mid-Waterford Coast SPA,Cork Harbour SPA,Blackwater Estuary SPA,Dungarvan Harbour SPA,Ballymacoda Bay SPAPart of the 4km corridor lies within 2km of Mid-Waterford Coast SPA, Cork Harbour SPA, Blackwater Estuary SPA, Dungarvan Harbour SPA and BallymacodaThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Bay SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. Between Muckridge and Tinnabinna the entire 4km corridor traverses the Blackwater Estuary SPA and Blackwater River (Cork/Waterforhabitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering this corridor should be as follows: 1. Where feasible the corridor will follow existing roads through the SPA and across the SAC; 2. Where engineering works to the bridge and roads through the SAC/SPAs would be required to render it suitable, an assessment would be required to ensure there was no loss of SAC habitat or of functionally-linked habitat that might affect the ability of the SPA to support its bird population. Construction must be timed to avoid the winter period. 3. Where engineering works to a road bridge across the Blackwater River SAC would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. They must be situated so that no loss of SAC plant species would arise. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or qualifying fish populations; 4. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC/SPA boundaries and/or must involve no loss of qualifying SAC habitat or supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
d) SAC and at Killongford it traverses Dungarvan Harbour SPA. Blackwater River SAC is designated for its estuaries, mudflats and sandflats not covered by seawater at low tide, perennial vegetation of stony banks, Salicornia and other annuals colonising mud and sand, Atlantic salt meadows, Mediterranean salt meadows, water courses of plain to montane levels with the Ranunculiond. A noise impact assessment of bridge construction regarding hen harrier, otter and qualifying fish species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that any improvements to existing roads through the SPA, or a new crossing of the Blackwater River, would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to divert to cross where the River Blackwater is narrower and/or to divert around the Dungarvan Harbour SPA between Killongford and Dungarvan to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
fluitantis and Callitricho- Batrachion vegetation, old sessile oak woods with Ilex and Blechnum in the British Isles, alluvial forests with Alnus glutinosa and Fraxinus excelsior, freshwater pearl mussel, white-clawed crayfish, sea lamprey, brook lamprey, river lamprey, twaite shad, salmon, otter and Killarney fern. Dungarvan Harbour SPA is designated for its great crested grebe, light- bellied brent
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
goose, shelduck, red- breasted merganser, oystercatcher, golden plover, grey plover, lapwing, knot, dunlin, black- tailed godwit, bar-tailed godwit, curlew, redshank, turnstone and its population of wetland and waterbirds. It would not be possible to make the connection to Waterford without traversing the River Blackwater SAC.
3 7Cork to FermoyBlackwater River (Cork/Waterford) SAC,CorkPart of the 4km corridor lies within 2km ofThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Harbour SPA,Blackwater Callows SPACork Harbour SPA and Blackwater Callows SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. At Ballinterry the entire 4km route corridor traverses the Blackwater River (Cork/Waterfor d) SAC.should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering this corridor should be as follows: 1. Where feasible the corridor will follow existing road bridges across the SAC; 2. Where engineering works to any bridge across the SAC would be required to render it suitable, an assessment would be required to ensure there was no loss of SAC habitat. 3. Where engineering works to a road bridge across the Blackwater River SAC would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. They must be situated so that no loss of SAC plant species would arise. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or qualifying fish populations; 4. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC boundary and/or must involve no loss of qualifying SAC habitat;
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
It would be possible to route around the SAC with a c. 12km diversion to the west.b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding hen harrier, otter and qualifying fish species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the Blackwater River, would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to divert to west around the SAC to demonstrate no adverse effect on site integrity.
3 8Cork to LimerickBlackwater River (Cork/Waterford) SAC,Lower River Shannon SAC,Tory Hill SAC,River Shannon and River Fergus Estuaries SPAPart of the 4km corridor lies within 2km of River Shannon and River Fergus Estuaries SPA. Since this site is designated for mobile species that may makeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. The entire 4km corridor traverses the Blackwater River (Cork/Waterfor d) SAC at Mallow. It would be possible to route around the SAC with a c. 12km diversion to the west.is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering this corridor should be as follows: 1. Where feasible the corridor will follow existing road bridges across the SAC; 2. Where engineering works to any bridge across the SAC would be required to render it suitable, an assessment would be required to ensure there was no loss of SAC habitat. 3. Where engineering works to a road bridge across the Blackwater River SAC would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. They must be situated so that no loss of SAC plant species would arise. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or qualifying fish populations; 4. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC boundary and/or must involve no loss of qualifying SAC habitat; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding otter and qualifying fish species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the Blackwater River, would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to divert to west around the SAC to demonstrate no adverse effect on site integrity.
3 9Limerick to WaterfordLower River Suir SAC,Lower River Shannon SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran withinThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Shannon SAC and Lower River Suir SAC.provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
However, any impact on movement of mobile riverine species could be avoided through use of existing road and crossing infrastructure.
4 0Limerick to KilkennySpahill And Clomantagh Hill SAC,Lower River Suir SAC,Lower River Shannon SAC,River Barrow And River Nore SAC,The Loughans SAC,Clare Glen SAC,River Nore SPA,Slievefelim to Silvermines Mountains SPAPart of the 4km corridor lies within 2km of River Nore SPA and Slievefelim to Silvermines Mountains SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location toThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering this corridor should be as follows: 1. Where feasible the corridor will follow existing roads through the SPA and across the SAC river;
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
affect functionally- linked land for SPA birds outside the SPA boundary. Between Newport and Kilcommon the entire 4km corridor encompasses the Slievefelim to Silvermines Mountains SPA and Lower River Shannon SAC. The SPA is designated for its hen harrier population. The reasons for SAC designation have already been given. At Birchhill the entire 4km corridor traverses the2. Where engineering works to the road would be required to render it suitable, an assessment would be required to ensure there was no loss of functionally-linked habitat that might affect the ability of the SPA to support its hen harrier population. Construction must be timed to avoid the sensitive season for hen harrier. 3. Where engineering works to a road bridge across the Lower River Shannon SAC or Lower River Suir SAC would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. They must be situated so that no loss of SAC plant species would arise. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or qualifying fish and dolphin populations; 4. If a new bridge is required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC/SPA boundaries and/or must involve no loss of qualifying SAC habitat or supporting habitat for SPA birds; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding hen harrier, otter and qualifying fish and dolphin species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Lower River Suir SAC. The SAC is designated for Atlantic salt meadows, Mediterranean salt meadows, water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho- Batrachion vegetation, Hydrophilous tall herb fringe communities of plains and of the montane to alpine levels, old sessile oak woods with Ilex and Blechnum in the British Isles, alluvial forests with Alnus glutinosa and Fraxinusdemonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that any improvements to existing roads through the Slievefelim to Silvermines Mountains SPA, or a new crossing of the River Shannon or Suir, would not be possible without an adverse effect on site integrity, the Corridor should be revised, such as to divert south of the SPA and north of the River Suir to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
excelsior, Taxus baccata woods of the British Isles and its populations of freshwater pearl mussel, white clawed crayfish, sea lamprey, brook lamprey, river lamprey, twaite shad, salmon and otter. It would be possible to route the corridor south of the SPA and north of the Lower River Suir SAC. However, it would not be possible to make the connection with Kilkenny without traversing the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Lower River Shannon.
4 1Kilkenny to PortlaoiseRiver Barrow And River Nore SAC,Lisbigney Bog SAC,River Nore SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding howThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Nore SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
4 2Kilkenny to CarlowRiver Barrow And River Nore SAC,River Nore SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impactsThe final route alignment should avoid any new construction within 200m of any European sites and within 200m of any European sites there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction- related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Nore SPA. Since these sites are designated for mobile species that may make
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
4 3Kilkenny to EnniscorthyBlackstairs Mountains SAC,River Barrow And River Nore SAC,Slaney River Valley SAC,River Nore SPA,Wexford Harbour and Slobs SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required)The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km ofhabitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
River Nore SPA and Wexford Harbour & Slobs SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
4 4Kilkenny to WaterfordLower River Suir SAC,River Barrow And River Nore SAC,River Nore SPAPart of the 4km corridor lies within 2km of River Nore SPA. Since this site is designated for mobile species that may makeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
4 5Waterford to TramoreLower River Suir SAC,Tramore Dunes and Backstrand SAC,Tramore Back Strand SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required)The final route alignment should avoid any new construction within 200m of any European sites and within 200m of any European sites there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction- related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Tramore Back Strand SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
4 6Enniscorthy to WaterfordLower River Suir SAC,River Barrow And River Nore SAC,Slaney River Valley SAC,Wexford Harbour and Slobs SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise andThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, orquality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
using standard mitigation methods). Part of the 4km corridor lies within 2km of Wexford Harbour and Slobs SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
4 7Waterford to WexfordLower River Suir SAC,River Barrow And River Nore SAC,Slaney River ValleyThe 4km corridor is sufficientlyThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SAC,Wexford Harbour and Slobs SPAwide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existingshould be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Wexford Harbour and Slobs SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally-
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
linked land for SPA birds outside the SPA boundary.
4 8Wexford to Rosslare EuroportCarnsore Point SAC,Slaney River Valley SAC,Wexford Harbour and Slobs SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions orThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Wexford Harbour and Slobs SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
4 9Enniscorthy to WicklowBuckroney-Brittas Dunes And Fen SAC,The Murrough Wetlands SAC,Slaney River Valley SAC,Wexford Harbour and Slobs SPA,Wicklow Head SPA,The Murrough SPAPart of the 4km corridor lies within 2km of Wexford Harbour and Slobs SPA, Wicklow Head SPA and the Murrough SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycleThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of several SPAs. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented. The approach to delivering this corridor should be as follows: 1. Where feasible the corridor will follow existing road bridges across the SAC;
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary. At Enniscorthy, Clovass and Clonhenret the entire 4km corridor traverses the Slaney River Valley SAC. The SAC is designated for estuaries, mudflats and sandflats not covered by seawater at low tide, Atlantic salt meadows, Mediterranean salt meadows, water courses of plain to2. Where engineering works to any bridge across the SAC would be required to render it suitable, an assessment would be required to ensure there was no loss of SAC habitat. 3. Where engineering works to a road bridge across the Slaney River would be required to render it suitable, any permanent works must remain out of the water column, unless it can be demonstrated this would not affect site integrity, and must not hinder potential for otter passage along the riverbanks. If any temporary ‘in river’ works were to be necessary, studies (including but not limited to underwater noise and hydrodynamic studies), and potentially mitigation, would be required to ensure the works could be delivered without an adverse effect on the SAC habitats or qualifying fish or seal populations; 4. If any new bridges are required, the following general requirements must be followed in designing and assessing the structure: a. Any abutments must be located outside the SAC boundary and/or must involve no loss of qualifying SAC habitat; b. Any abutments must be located outside the river channel and must be set sufficiently far back from the bank top to ensure passage of otter along the banks is not prevented; c. The soffit of the bridge should be sufficiently high that significant shading impacts on the water column and in river vegetation will not arise. Research suggests this would require a soffit height: deck width ratio of 0.7 or above. d. A noise impact assessment of bridge construction regarding otter and qualifying fish and seal species will be required, and potentially mitigation (such as seasonal restrictions on working, alternative construction methods or noise control techniques) to ensure no significant effect on the population of any species. e. Water quality protection measures will be required as well as a hydrological study to confirm any new construction would not affect special interest features that are hydrologically sensitive (e.g. alluvial woodland). f. Lighting should be avoided in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If detailed design work indicates that a new crossing of the Blackwater River, would not
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
montane levels with the Ranunculion fluitantis and Callitricho- Batrachion vegetation, old sessile oak woods with Ilex and Blechnum in the British Isles, alluvial forests with Alnus glutinosa and Fraxinus excelsior and its populations of freshwater pearl mussel, sea lamprey, brook lamprey, river lamprey, twaite shad, salmon, otter and harbour seal. It would be possible to avoid anybe possible without an adverse effect on site integrity, the Corridor should be revised, such as to divert east around the SAC to demonstrate no adverse effect on site integrity.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
crossings of the SAC by moving the corridor approximately 4km to the east.
5 0Wicklow to BrayThe Murrough Wetlands SAC,Bray Head SAC,Wicklow Head SPA,The Murrough SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through eitherThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Since a large part of the 4km corridor either overlaps with, or lies within 2km of several SPAs, there will need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Wicklow Head SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
5 1Bray to DublinSouth Dublin Bay SAC,Rockabill to Dalkey Island SAC,Ballyman Glen SAC,Bray Head SACSouth Dublin Bay and River Tolka Estuary SPA,Dalkey Islands SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final routeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of South Dublin Bay and Riverof the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Tolka Estuary SPA and Dalkey Islands SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
5 2Carlow to AklowSlaney River Valley SAC,River Barrow And River Nore SAC,The 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary.The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the mostconstruction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Slaney River Valley SAC and River Barrow and River Nore SAC.
5 3Carlow to PortlaoiseRiver Barrow And River Nore SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise ifThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable.. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Barrow
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
and River Nore SAC.
5 4Tullamore to PortlaoiseCharleville Wood SAC,River Barrow And River Nore SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding howThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of the River Barrow and River Nore SAC.
5 5Mullingar to TullamoreCharleville Wood SAC,Split Hills And Long Hill Esker SAC,Lough Ennell SAC,Lough Ennell SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore,The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrainednew construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Lough Ennell SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
5 6Edenderry to PortlaoiseRiver Barrow And River Nore SACThe 4km corridor is sufficientlyThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existingshould be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Barrow and River Nore SAC.
5 7Newbridge to NaasN/AN/ANo constraints or mitigation needed.
5 8Portlaoise to NewbridgeRiver Barrow And River Nore SAC,Pollardstown Fen SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbanceThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigationensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
methods). Part of the 4km corridor lies within 2km of River Barrow and River Nore SAC.
5 9Naas to BlessingtonRed Bog, Kildare SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidableThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Although part of the 4km corridor lies within 2km of Red Bog SAC, impacts on the SAC will be avoidable through keeping the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
final route alignment over 200m from the SAC to avoid air quality impacts and ensuring any new construction takes account of, and avoids, any hydrological impacts for the SAC.
6 0Edenderry to NaasBallynafagh Bog SAC,Ballynafagh Lake SAC,The Long Derries, Edenderry SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required)The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Although part of the 4km corridor lies
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
within 2km of Ballynafagh Bog SAC, Ballynafagh Lake SAC,The Long Derries and Edenderry SAC, impacts on the SAC will be avoidable through keeping the final route alignment over 200m from the SACs to avoid air quality impacts and ensuring any new construction takes account of, and avoids, any hydrological impacts for the SACs.
6 1Mullingar to EdenderryRiver Boyne And River Blackwater SAC,Wooddown BogThe 4km corridor is sufficientlyThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SAC,Mount Hevey Bog SAC,River Boyne and River Blackwater SPAwide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existingshould be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Boyne and Blackwater SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SPA birds outside the SPA boundary.
6 2Mullingar to MaynoothRiver Boyne And River Blackwater SAC,Wooddown Bog SAC,Rye Water Valley/Carton SAC,Mount Hevey Bog SAC,River Boyne and River Blackwater SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisionsThe final route alignment should avoid any new construction within 200m of any European sites and within 200m of any European sites there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction- related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Boyne and Blackwater SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
6 3Navan to MullingarRiver Boyne And River Blackwater SAC,Wooddown Bog SAC,Mount Hevey Bog SAC,River Boyne and River Blackwater SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site,The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Boyne and Blackwater SPA. Since this site is designated for mobile species
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
6 4Dunboyne to LeixlipRye Water Valley/Carton SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if constructionThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Although part of the 4km
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
corridor lies within 2km of Rye Water Valley/Carton SAC, impacts on the SAC will be avoidable through keeping the final route alignment over 200m from the SACs to avoid air quality impacts and ensuring any new construction takes account of, and avoids, any hydrological impacts for the SACs.
6 5Maynooth to LeixlipRye Water Valley/Carton SACThe 4km corridor is sufficiently wide that direct impacts on any European sitesThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating newproject level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
infrastructure in the most constrained sections, or using standard mitigation methods). Although part of the 4km corridor lies within 2km of Rye Water Valley/Carton SAC, impacts on the SAC will be avoidable through keeping the final route alignment over 200m from the SACs to avoid air quality impacts and ensuring any new construction takes account of, and avoids, any
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
hydrological impacts for the SACs.
6 6Leixlip to CellbridgeRye Water Valley/Carton SACThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisionsThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Although part of the 4km corridor lies within 2km of Rye Water Valley/Carton SAC, impacts on the SAC will be avoidable through keeping the final route alignment over 200m from the
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SACs to avoid air quality impacts and ensuring any new construction takes account of, and avoids, any hydrological impacts for the SACs.
6 7Dublin to LeixlipRye Water Valley/Carton SAC, South Dublin Bay and River Tolka Estuary SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final routeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of South Dublin Bay & Riverof the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Tolka Estuary SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
6 8Naas to DublinN/AThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise andNo constraints or mitigation needed.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
using standard mitigation methods).
6 9Swords to Dublin AirportMalahide Estuary SAC/SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisionsThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of a Malahide Estuary SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods).
7 0Celbridge to DublinN/AThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impactsThere are no European sites within the corridor. However, South Dublin Bay SAC and SPA are 3km from the eastern end of the proposed corridor, which lies within urban Dublin. Published guidance regarding distances from SPA boundaries at which habitat for brent goose is likely to be significant in sustaining populations (Natural England, 2009) cites an impact risk zone of 2km from the designated site, which the corridor exceeds. Moreover, given the nature of a cycle way even new construction would be likely to result in insignificant levels of habitat loss from supporting habitat, if any. Nonetheless, based on local data for the Dublin area regarding brent geese (https://www.pleanala.ie/publicaccess/EIAR- NIS/305680/Environmental/Appropriate%20Assessment/Natura%20Impact%20Statem ent.pdf) it is clear that there are Brent goose sites within the 4km corridor. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats. In such a situation
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
(if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods).wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
7 1Grand Canal GreenwayN/AThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections ofThere are no European sites within the corridor. However, South Dublin Bay SAC and SPA are 2.5km from the eastern end of the proposed corridor, which lies within urban Dublin. Published guidance regarding distances from SPA boundaries at which habitat for brent goose is likely to be significant in sustaining populations (Natural England, 2009) cites an impact risk zone of 2km from the designated site, which the corridor exceeds. Moreover, given the nature of a cycle way even new construction would be likely to result in insignificant levels of habitat loss from supporting habitat, if any. Nonetheless, based on local data for the Dublin area regarding brent geese (https://www.pleanala.ie/publicaccess/EIAR- NIS/305680/Environmental/Appropriate%20Assessment/Natura%20Impact%20Statem ent.pdf) it is clear that there are Brent goose sites within the 4km corridor. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods).
7 2Dublin port to Heuston Station via Connolly stationSouth Dublin Bay and River Tolka Estuary SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise ifThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of South Dublinis required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Bay & River Tolka Estuary SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
7 3Swords to DublinMalahide Estuary SAC, South Dublin Bay and River Tolka Estuary SPA, Malahide Estuary SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore,The final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also need to be consideration at the project level of any detailed design requirements (such as prevention of access) that will ensure no net increase in recreational pressure within the European site. If any new construction within 200m is needed to create the cycle route a noise and air quality
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrainedassessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of South Dublin Bay & River Tolka Estuary SPA and Malahide Estuary SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
outside the SPA boundary.
7 4Navan to SwordsRiver Boyne And River Blackwater SAC, Malahide Estuary SAC, Malahide Estuary SPA, River Boyne and River Blackwater SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding howThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Boyne & River Blackwater SPA and Malahide Estuary SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
7 5Balbrigan to SwordsRogerstown Estuary SAC, Rockabill to Dalkey Island SAC, Malahide Estuary SAC, Skerries Islands SPA, Malahide Estuary SPA, Rogerstown Estuary SPA, Rockabill SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final routeThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Since a large part of the 4km corridor either overlaps with, or lies within 2km of several SPAs, there will need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Skerries Islands SPA, Malahidewintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Estuary SPA, Rogerstown Estuary SPA and Rockabill SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
7 6Drogheda to BalbrigganRiver Boyne And River Blackwater SAC, Boyne Coast And Estuary SAC, River Nanny Estuary and Shore SPA, Boyne Estuary SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoidedThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure inwill assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of River Nanny Estuary and Shore SPA and Boyne Estuary SPA Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
outside the SPA boundary.
7 7Navan to DroghedaRiver Boyne And River Blackwater SAC, Boyne Estuary SPA, River Boyne and River Blackwater SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding howThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Boyne Estuary SPA and River Boyne & Blackwater SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
7 8Dundalk to DroghedaRiver Boyne And River Blackwater SAC, Dundalk Bay SAC, Boyne Coast And Estuary SAC, Clogher Head SAC, Boyne Estuary SPA, Dundalk Bay SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran withinThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lies within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Boyne Estuary SPA and Dundalk Bayprovided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
7 9Cavan to NavanRiver Boyne And River Blackwater SAC, Killyconny Bog (Cloghbally) SAC, River Boyne and River Blackwater SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visualThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standardensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
mitigation methods). Part of the 4km corridor lies within 2km of River Boyne & Blackwater SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
8 0Longford to CavanLough Oughter And Associated Loughs SAC, Clooneen Bog SAC, Lough Forbes Complex SAC,The 4km corridor is sufficiently wide that directThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
Lough Oughter SPA, Ballykenny- Fisherstown Bog SPAimpacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructuredemonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Lough Oughter SPA and Ballykenny- Fisherstown Bog SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
functionally- linked land for SPA birds outside the SPA boundary.
8 1Armagh to CavanLough Oughter And Associated Loughs SAC, Kilroosky Lough Cluster SAC, Lough Oughter SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routingThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Lough Oughter SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
8 2Dundalk to MonaghanDundalk Bay SAC, Kilroosky Lough Cluster SAC, Dundalk Bay SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran withinThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Dundalk Bay SPA. Since this site isprovided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
8 3Dundalk to ArmaghDundalk Bay SAC, Dundalk Bay SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and airThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Partlie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
of the 4km corridor lies within 2km of Dundalk Bay SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
8 4Dundalk to Carrickmacro ssDundalk Bay SAC, Dundalk Bay SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoidedThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections of cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure inwill assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Dundalk Bay SPA. Since this site is designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
8 5Newry to DundalkCarlingford Shore SAC, Dundalk Bay SAC, Carlingford Mountain SAC, Carlingford Lough SPA, Dundalk Bay SPAThe 4km corridor is sufficiently wide that direct impacts on any European sites can be avoided if necessary. Therefore, while noise and visual disturbance impacts, and air quality impacts (if construction was required) could arise if the final route ran within 200m of a European site, these impacts are avoidable through either routing decisions or decisions regarding how the relevant sections ofThe final route alignment should avoid any new construction within 200m of any European sites as a first preference. Where European sites are to be traversed existing roads and bridges should be used to carry the cycle route where feasible and there should be no new lighting introduced in areas that are currently unlit unless it can be demonstrated that there would be no adverse effect on site integrity. Where the cycle route will traverse a European site there will also be a need for consideration at the project level of any detailed design requirements (such as prevention of access) that will assess the potential impact of any possible net increase in recreational access to, or pressure within, the European site and determine if it is considered acceptable. If any new construction within 200m is needed to create the cycle route a noise and air quality assessment (and potentially noise and air quality mitigation) will be required to ensure there is no construction-related disturbance that could significantly affect SPA birds or significant air pollution impacts on sensitive habitats. Parts of the 4km corridor lie within 2km of an SPA. There will therefore need to be consideration of any potential for loss of functionally-linked habitat for SPA birds once the actual cycle route is determined. This will only be required if new construction is required within natural habitats and loss of habitat is greater than trivial; this is relevant because very little land is required for a cycle route. In such a situation wintering bird surveys to determine use of the habitats by SPA birds may be required and, if necessary, appropriate mitigation provided to ensure no adverse effect on the integrity of the European site before the works are consented.
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
cycle route will be created (e.g. utilising existing infrastructure rather than creating new infrastructure in the most constrained sections, or using standard mitigation methods). Part of the 4km corridor lies within 2km of Dundalk Bay SPA and Carlingford Lough SPA. Since these sites are designated for mobile species that may make use of habitat outside the SPA boundary there is potential for any new cycle
Corridor Number and NameEuropean Sites wholly or partially within the 4km NCN Proposed CorridorConsideration of potential impactsMitigation approach for Corridor
route construction in this location to affect functionally- linked land for SPA birds outside the SPA boundary.

Appendix D European Sites and NCN Corridors

Figure from page 1101

Figure from page 1101

Figure from page 1102

Figure from page 1102

Figure from page 1103

Figure from page 1103

Figure from page 1104

Figure from page 1104

Figure from page 1105

Figure from page 1105

Figure from page 1106

Figure from page 1106

C

y

l

a

c

n

l

e

o

N

i

t

a

e

N

t

w

c

L

o

í

o

í

a

n

h

r

a

t

o

N

R

á

a

i

s

t

i

n

ú

Figure from page 1107

Figure from page 1107

Department of Transport 2 Leeson Lane, Dublin, D02 TR60 T: (01) 670 7444 W: www.gov.ie/transport/

Pages 928–1107 · View in original PDF