2.3.1Freeing Ports .1In fishing operations, especially when towing, or hove-to when attending to pots or nets, a

problem can arise with decked vessels having fixed bulwarks, whereby water is shipped over the bulwark into the enclosed deck. This not only creates uncomfortable working conditions, but more dangerously, can lead to the accumulation of water and consequential down flooding into enclosed or below-deck spaces, and create a detrimental effect on stability by the introduction of “free surface effect” particularly on a large deck area. It is essential, therefore, that means of rapidly clearing entrapped water is fitted in all vessels with fixed bulwarks. At the same time, however, the means of clearing water must not provide easy access for water to enter the enclosed deck. .2Means to clear entrapped water may comprise any, or any combination, of the following:

a.Freeing ports with an attached means of closing (provided that the freeing port is only

closed during fishing operations). b.Permanent openings in the bulwarks, such as slots. c.Apertures in and under bulwark, or stern ramp doors. d.Deck scuppers, where the discharge is above the load waterline.

.3The total area of the water freeing arrangements should be a minimum of 3% of the area of the

fixed bulwarks enclosing the deck or space under consideration. .4Any freeing port, or slot, in the bulwark must have the bottom edge as close to the deck as

possible. Freeing ports greater than 230mm in depth and wider than 500mm must be fitted with bars.

.5Where freeing ports are fitted with hinged flaps or shutters, there must be sufficient clearance to

prevent jamming, and the hinges must be fitted with pins of non-corrodible material.

.6The freeing ports must be arranged throughout the length of the bulwark or well, to give

maximum drainage under all normal conditions of trim.

.7Care must be taken that deck pounds, machinery and net or gear stowage do not impede the free

flow of trapped water to the freeing ports or slots.

.8Lift-up closing appliances fitted to freeing ports must be so arranged that they are secure in the

open position and will not float off from the stowed positions.

.9See also section 13.1.4.2 of Annex 2 (Guidance on Capsize Safety), regarding freeing ports.

3STABILITY

3.1Part A – Pre-2004 fishing vessels

3.1.1General .1Adequate margins of freeboard and stability must be provided for the safe operation of the vessel.

.2It is the Master’s responsibility to ensure that the vessel is operated in accordance with paragraph

3.1.1.1.