1 Executive Summary
Text from page 4 of the source PDF is machine-read (OCR) from a scanned image and may contain recognition errors.
1Executive Summary
This Progress Report on the Climate Action Plan (CAP) 2025 details progress on the new
actions that were due for completion in Q4 2025. In total, 16 of the 37 new Q4 actions
have been delivered on time (Table 1).
2 of the 17 delayed actions from Q1, Q2 and Q3 were also delivered in Q4 (Table 2).
Overall implementation of CAP25 stands at 46 actions out of 82 completed by year end.
High impact actions delayed from CAP24 and CAP23 are also included in this report. Of
the 43 legacy actions remaining, 5 were completed in Q4 2025 (Table 3).
Delays in climate action delivery in Q4 are attributed to several factors including: time
required for legislative responses; delays arising from public consultation; and
dependencies on other actions or policies. These delays threaten Ireland’s ability to meet
binding emissions targets and risk increasing future pressures, costs, environmental
damage and reputational harm. While delivery results in 2025 show that a lot has been
achieved, we need to increase efforts if Ireland is to close the emissions gap.
All delayed and legacy actions will continue to be reported upon into 2026, maintaining
visibility as to their delivery.
To provide more detail on progress, risks and delivery profiles, this report is organised
into sectoral chapters in order of emissions share, with a further chapter on cross-cutting
activity. As in previous progress reports, attention is given to Key Performance Indicators
(KPIs), national emissions trends and projections.
Information on each reportable action from the CAP25 Annex of Actions is contained at
Appendix 1.
To keep up to date with the Government’s Climate Action Initiatives, subscribe to the
monthly Climate Action Newsletter mailing list here.
Table 1 Delivery by Department on new Q4 2025 actions
DCEE 3 13 DAFM 3 5 D/Transport 5 12 DHLGH fe) 1 DETE 3 3 DFHERIS fe) 1 DPER 1 1 DFIN 1 1 TOTAL 16 37
Table 2 Delivery by Department on delayed Q1, Q2 & Q3 CAP 2025 actions due in Q4 2025
DCEE fe) 9 DAFM 1 1 D/Transport 1 5 DHLGH fe) 2 TOTAL 2 17
Table 3 Delivery by Department on legacy actions due for reporting in Q4 2025
DCEE 1 24 DAFM 3 5 D/Transport fe) 7 DHLGH 1 2 DPER fe) 3 DETE fe) 2 TOTAL 5 43