1.2.2 Overcoming delays to climate action delivery
In total, 63 actions are reported as delayed at the end of 2024, including 45 actions from CAP24
and 18 remaining legacy high impact actions from CAP23. The most common reasons reported
by Departments for delivery delays, in order of impact, include:
Technical aspects: adding complexity and/or the need for further data or research;
Issues of alignment: whereby action delivery is dependent on other actions or EU/national policy
completing first;
Discrete issues: including slight delays that are due to resolve shortly and more isolated cases of delay
including difficulties in legal drafting, supply chain issues, and/or a change of direction in the action
approach;
Unexpected need for further engagement: be it stakeholder, public or internal consultation/dialogue;
Administrative delays: particularly the final clearance required for actions to complete, including
government approval; and/or
Capacity and Capability constraints: including resourcing, procurement delays arising from a reliance on
external consultants and competing work priorities.
Delays in climate action delivery must be urgently overcome to accelerate progress and
close gaps towards legally-binding emissions reduction targets under international, EU
and national regimes. The inability to identify and complete climate actions now will
result in steeper trajectories to bring Irish sectors, society and the economy back on
track, with reputational, litigation and cost implications associated with failing to do so.
All 63 delayed actions will carry forward for delivery and reporting with new actions
from CAP25, retaining commitment to high impact uncompleted actions.

Figure from page 12
Ministers Foley and Smyth launching Schools PV Programme Pilot (Courtesy of RTÉ)
Pages 11–12 · View in original PDF