1.2.2 Overcoming delays to climate action delivery
In total, 39 actions are reported as delayed in the first half of 2024, including 13 from CAP24
and 26 legacy high impact actions from CAP23. The most common reasons reported by
Departments for delivery delays include:
Need for further stakeholder engagement, including public consultation or internal consensus building
within working groups, departments and agencies;
Layers of administrative clearance, whereby actions are significantly advanced and are awaiting final
approval or publication (e.g. final drafts have been prepared or schemes are awaiting final launch) and
expect completion in Q3;
Issues of sequencing and alignment, whereby the completion of actions is reliant on the finalisation of
another activity or policy both at national and/or EU levels; and
Capacity and capability constraints, including internal resourcing issues and procurement delays arising
from a reliance on external expertise for climate policy or scheme development; and/or
Unexpected legal or technical complexity, often leading to the need for extra time for additional research,
outreach, legal drafting, and/or the development of new working approaches.
Delays in climate action delivery must be urgently overcome to work towards emissions
reduction targets at international, EU and national levels. Failure to complete climate
actions now will result in steeper trajectories and decarbonisation pathways to bring
sectors, society and the Irish economy back on track.
Page 11 · View in original PDF