1.2.1 Sectoral actions completed and delayed in Q4 2023

Examples of high impact sectoral actions completed and delayed in Q4 2023 are detailed in

Tables 4 and 5. With significant potential for direct emissions reduction, they are further

expanded upon in sectoral chapters throughout this progress report. Information on every

reportable action is detailed at Appendix 1.

Table 4 Examples of high impact sectoral actions and sub-actions completed in Q4 2023

SectorAction / sub-action completed in Q4 2023
AgricultureRE/23/1/A: Establish Teagasc Signpost Advisory Service
TransportTR/23/41: Accelerate delivery of National Transport Authority (NTA) Connecting Ireland (rural public transport services)
TR/23/7: Progress targeted campaign to support uptake of EVs
ElectricityEL/23/15: Publish public consultation on private wires
BuildingsBE/23/5: Provide a record budget allocation for Sustainable Energy Authority of Ireland (SEAI) retrofit schemes
BE/23/11: Deliver retrofits to c.2,400 Local Authority homes
LULUCFLU/23/15: Continue to rehabilitate former peatland production land

Table 5 Examples of high impact sectoral actions and sub-actions delayed in Q4 2023

SectorAction / sub-action delayed in Q4 2023
AgricultureAG/23/10: Develop proposal for a cow reduction or an exit scheme
AG/23/13: Deliver National Biomethane Strategy (delayed from Q3)
TransportTR/23/19: Publish National Transport Demand Management Strategy
ElectricityEL/23/2: Publish the Renewable Electricity Spatial Policy Framework (delayed from Q3)
EL/23/13/B: Launch Small Scale Generation Scheme
EL/23/24: Publish Electricity Demand Side Strategy
BuildingsBE/23/26: Publish National Heat Policy Statement (delayed from Q3)
BE/23/31: Publish roadmap on the retrofit of commercial buildings (delayed from Q3)
LULUCFLU/23/20/A: Interim reporting to Government on Land Use Review Phase 2
IndustryEN/23/3: Prepare a decarbonisation roadmap for industrial heat
EN/23/6: Conduct feasibility assessment on carbon capture & storage

Pages 8–9 · View in original PDF