Transportation & Urban Regeneration Strategic Policy Committee
27th May 2025, Blackwater Room, Buvinda House, Dublin Rd, Navan, C15 Y291. 2.30 pm – 16.15pm.
Attendance
Councillors
- Cllr Sean Drew (SD), Acting Chair
- Cllr Paddy Meade (PM)
- Cllr Amanda Smith (AS)
- Cllr Caroline O’Reilly (COR) via Teams
- Cllr Wayne Harding (WH) via Teams
Sectoral Representatives
- Mr. Dave Anderson (DA) PPN Rep
- Ms. Josephine Reynolds O’Connor (JROC), PPN Rep
- Ms. Paula Mc Caul (PMC) PPN Rep via Teams
Absent / Apologies
- Cllr Mike Bray (MB) Chair
Officials
- Martin Murry (MM), DOS
- Caroline Corrigan (CC) Senior Engineer
- Mr. Nicholas Wyatt (NW) Senior Engineer
- Mr. John McGrath (JMcG), Senior Engineer
- Joan Carroll (JC) Acting Senior Executive Officer
- Lorraine Sherrock (LS), Acting Administrative Officer
Presenters
- Caroline Corrigan - Senior Engineer – Footpath Extension Programme & Abandonment of unused public roads
- John McGrath -Senior Engineer- Regeneration Team – Ongoing Projects
Agenda items
0.0 In accordance with the Terms of Reference, a nomination was sought from the Chair who could not {#item-0-0}
attend, for a Cllr to act as Chair on his behalf. Cllr Mike Bray nominated Cllr Sean Drew (SD) Cllr Sean Drew (SD) was proposed as Acting Chair by Cllr Paddy Meade and Seconded by Cllr Amanda Smith (AS).
1.0 Minutes of Previous Meeting 20th February 2025 {#item-1-0}
Proposed by; Cllr Paddy Meade (PM)
Seconded by: Cllr Amanda Smith (AS) One Typo duly corrected. (DV) changed to (DA) in respect of Committee member Mr. Dave Anderson.
2.0 Matters Arising from Minutes {#item-2-0}
No matters arising.
3.0 Agenda Items referred to the SPC through the Full Council or MD Meetings {#item-3-0}
None
4.0 The Roadworks Programme – Schedule of Municipal District Works - Active Travel Operational vs {#item-4-0}
Capital Budget A verbal explanation was given by CC in relation to the Schedule of Municipal District Works and funding streams. The Roadworks Programme is ahead of schedule this year. DA queries what percentage of the budget is for maintenance and what percentage is for improvements. MM clarified that funding is not allocated in this manner. The budget is adopted by the members on an annual basis. DA asked for an update on the existing cycle network. MM said that could be provided. SD asked if the tender and costs were relative to last year and if all of the work agreed by the full Council will be done. MM advised that the prices received were in line with projected costs and all of the proposed works will be completed. Depending on how the contracts go, some minor additional work may be possible. This will be communicated to Members.
5.0 Road Safety initiatives / Traffic Calming Measures - The Road Safety plan 2021-2030 {#item-5-0}
CC gave a verbal update on road safety initiatives / traffic calming measures. She advised that the National Road Safety Plan will be delivered in 3 stages up to 2030 and that MCC will develop its plan based on the provisions of the National Plan & local issues. MM clarified that the delays are due to GDPR issues surrounding collision data which is being addressed at Oireachtas level. MM advised that Traffic Calming is a statutory function for each LA to have an individual plan tailored to their specific needs. Technical solutions are based on data / statistics collected. The rationale as to how the Transport Dept comes up with the calming measures can be presented to this committee. PM raised a question in relation to why there is a variance on the use of ramps in villages in neighbouring counties. For example, in Louth most villages have ramps as a calming measure but this is not the case in Meath. AS agreed, in relation to ramps being places at schools. COR asked for a list of schools or locations that may need traffic calming measures. MM advised that this was being looked at under the footpath extension programme. With the permission of the Chair, the presentation listed under Item 12 on the agenda was presented to the Committee.
6.0 Active Travel - Active Travel Strategy {#item-6-0}
NW gave a brief explanation in relation to the Active Travel Programme and how works and maintenance of active travel infrastructure are funded. DA queries how the Greater Dublin Area (GDA) Transport Strategy affects Meath as Navan is mentioned in it. Meath’s transport Strategy is contained in Chapter 5 of the County Development Plan (CDP) – Movement Strategy. It contains the vision, policy context, policies, objectives, metrics and other elements of a strategy that you would expect to find, which in turn informs the work programmes and action plans that are formulated by the Transportation Department. NW explained that both the CDP and the Climate Action Plan take the GDA Transport strategy among other plans, strategies, and guidelines into account. A brief discussion ensued.
7.0 Public Transport {#item-7-0}
No update
8.0 Navan Rail Line {#item-8-0}
Scheme is progressing, no update
9.0 Roads & Sustainable Transport Schemes {#item-9-0}
No update
10.0 Public Lighting {#item-10-0}
The Public Lighting Energy Efficiency Project (PLEEP) Scheme is not progressing well. Kilkenny County Council is managing the contract and KLS is the company contracted to do the work. Work was to commence in Meath 16 months ago and should now be commencing next week. There is a nonperforming contractor in place. There could be delays of up to two years.
11.0 Presentation on Abandonment of unused public roads in accordance with Section 12 of the Roads {#item-11-0}
Act, 1993 CC gave a presentation on the abandonment of local tertiary unused roads and advised that these roads are unused or are now impassible historical roads that have not been used for many years. Many of the roads identified are now overgrown. CC outlined the statutory process to abandon the road and that the right of way would not be extinguished. PM did not agree with the abandonment of roads and has had issues with this in the past. As the SPC is for Policy decisions PM was asked to discuss his concerns in relation to specific cases with MCC officials separately. DA asked if when roads are abandoned, they could be turned into footpaths, MM said he would revert with an answer. CC reassured the Committee that the roads being looked at are extremely rural. PMC asked If the land was being offered back to the adjoining landowner, and she was advised that land transfer was not being proposed at this point but could be accommodated. The committee agreed in principle to commence the process. DA was agreeable on condition that the right of way was not being extinguished. PM asked that his opposition be noted.
Proposed by : Cllr Amanda Smith (AS)
Seconded by : Cllr Sean Drew (SD)
12.0 Presentation on proposed Footpath Extension Programme {#item-12-0}
CC gave a presentation on the proposed footpath extension programme. 138 schools surveyed in Meath, 24 post primary are located in urban areas and of the 114 primary schools, many are rural locations. 30 primary schools spread across the county are without footpaths of which 9 of these locations have been identified as schools that could be linked with footpaths. This presentation is not related to safety at school, it is solely on how a policy decision can be made to look at the 9 school locations that have been identified as candidates worth considering to form part of a footpath extension programme. A detailed design will need to be undertaken for each scheme. Cost estimates were presented with a large amount of cost relating to land acquisition and public lighting. AS & PM queried specific paths. CC agreed to review these after the meeting. Acceptance of the Footpath extension Programme was agreed by the Committee.
Proposed by: Cllr Paddy Meade
Seconded by: Cllr Amanda Smith
13.0 Presentation on Urban Regeneration – Ongoing Projects {#item-13-0}
JMcG gave an informative presentation on ongoing Urban Regeneration projects, such as St. Patrick’s Classical School / County Archive, Andy Brenna Park, Spicer’s Bakery and the Flowerhill Rejuvenation Projects. A discussion was had on funding being allocated to various towns within the Urban and Rural areas of the County under various different funding Schemes.
14.0 Correspondence & Circulars {#item-14-0}
None
15.0 AOB {#item-15-0}
SD raised a query in relation to speed vans within the County and whether MCC has any input into the locations and if the Council liaises with the Gardaí. He queried if MCC should have a policy to engage with these representatives and stakeholders. MM advised that the Council does not have a direct role but can have an input. Members Notices and Motions can be submitted to the relevant groups. MM will come back on whether a policy can be formulated to address this query. SD raised a query on how LIS schemes are decided on and how a scheme can be put forwarded on to the list. MM advised that yearly multiple applications are made to the Dept / DOT / TII. The council would have a priority list, but it would depend on what priority the inspector would allocate. The Council’s priority list can be shared with this group. PM welcomed the presence of the Gardaí and a checkpoint in his area. He also raised the issue of noncompliance with hedge cutting notices and whether the Council would now look at proceeding with prosecutions for failure to comply with said notices. He would like those prosecutions published in the newspaper.
Meeting ended @16.15pm